How to Create a Monthly Resource Cost Forecast in Microsoft Project
Question details
The user wants to generate a report showing the expected monthly resource costs for completed tasks within a project plan.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Tracking and reporting expected resource costs on a monthly basis for accurate budget forecasting.
- Observed behavior
- The goal is to accurately forecast and extract task-level resource costs per month for planning and reporting purposes.
Ensure that your project plan has resources properly assigned with defined cost rates, and that all tasks have accurate estimated durations and logical dependencies before generating the forecast.
Generate Monthly Cost Forecasts using Usage Views
The most effective way to view monthly expected costs natively in Microsoft Project is by utilizing the built-in Task Usage or Resource Usage views and configuring the timescale.
To get reliable tracking, it is critical to avoid manually entered dates or constraints. Using auto-scheduled tasks and logical dependencies ensures your forecast remains dynamic and accurate as project variables change.
Ensure all project tasks are set to auto-schedule and use logical dependencies instead of manual constraints for accurate forecasting.
Go to the 'Project' tab on the ribbon and select 'Set Baseline' to establish your planned tracking metrics.
Navigate to the 'View' tab and select either 'Task Usage' or 'Resource Usage' to see the time-phased data grid.
Right-click the time-phased grid on the right side, select 'Timescale', and set the bottom tier units to 'Months'.
Right-click the details column in the time-phased grid and select 'Cost' to display the expected monthly costs for each task or resource.
Export Cost Data to Excel for Custom Reporting
If you need to format, chart, or manipulate the monthly cost forecast further, exporting the usage data to a spreadsheet application is highly recommended.
Manage Your Project Cost Reports with WPS Office
While Microsoft Project handles the complex scheduling, you can seamlessly analyze, chart, and present your exported monthly cost forecasts using WPS Spreadsheet. WPS Office is a free, lightweight, and highly compatible alternative for all your data reporting and document needs.
- 1. Download and install: Download WPS Office for free from the official website and install it on your device.
- 2. Open your exported report: Launch WPS Spreadsheet and go to 'File' > 'Open' to load the cost report exported from Microsoft Project.
- 3. Analyze and format: Use WPS Spreadsheet's built-in PivotTables and chart tools to format your monthly resource forecast professionally.

Frequently Asked Questions
Why are my expected costs not showing up in the Task Usage view?
Ensure that you have assigned standard or overtime cost rates to your resources in the Resource Sheet, and that those resources are actively assigned to tasks with estimated work hours.
Can I view resource costs by week instead of by month?
Yes, you can adjust the time-phased grid timescale by right-clicking the grid header, selecting 'Timescale', and changing the bottom tier units from 'Months' to 'Weeks'.
Does saving a baseline affect my current cost forecast?
Saving a baseline simply captures the planned costs at that specific moment. As your project progresses and actual costs or durations change, comparing the current expected costs against your baseline helps you track budget variances.
How do I prevent tasks from shifting unexpectedly when calculating costs?
Use auto-scheduled tasks and rely on logical dependencies (such as Finish-to-Start) rather than manually entering date constraints. This allows the software to accurately calculate expected costs based on dynamic task durations.