Fix Microsoft Project Bulk Task Changes Not Applying
Question details
The user is unable to successfully apply bulk edits to selected tasks using the Multiple Task Information dialog in Microsoft Project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Attempting to modify properties for multiple tasks simultaneously using the Multiple Task Information dialog.
- Observed behavior
- Changes made within the Multiple Task Information dialog fail to apply to the selected tasks whenever summary lines are included in the user's selection.
Ensure your project task list is fully expanded so you can clearly distinguish between summary lines and actionable subtasks before making bulk selections.
Exclude Summary Tasks from Your Selection
Deselect any summary lines before opening the Multiple Task Information dialog so that your bulk edits apply successfully to the subtasks.
Summary lines in Microsoft Project are not ordinary tasks. By default, they are set to 'Fixed Duration' and calculate their values automatically based on their underlying subtasks. When you include summary tasks in a bulk selection, it prevents the Multiple Task Information dialog from correctly applying manual changes to the group.
Look at your highlighted tasks in the Gantt Chart or Task Sheet view to identify if any bolded summary tasks are included.
Hold down the 'Ctrl' key on your keyboard and click on any highlighted summary lines to remove them from your active selection.
Alternatively, you can manually highlight only the specific subtasks you wish to modify by holding 'Ctrl' and clicking each individual subtask, bypassing the summary rows entirely.
Right-click one of the selected subtasks and choose 'Information', or press 'Shift + F2' to open the Multiple Task Information dialog box.
Make your desired changes in the dialog box (such as assigning resources or changing task modes) and click 'OK'. The modifications will now successfully apply to all selected subtasks.

Manage Your Projects Efficiently with WPS Office
While Microsoft Project is a specialized tool for complex scheduling, WPS Spreadsheet offers an excellent, lightweight alternative for daily project tracking, Gantt chart creation, and task management. It is fully compatible with Microsoft Office formats and provides hundreds of free, ready-to-use project management templates.
- 1. Download and Install: Download WPS Office for free from the official website and install it on your device.
- 2. Explore Templates: Open WPS Office, navigate to the Templates section, and search for 'Project Management' or 'Gantt Chart'.
- 3. Start Planning: Select a template that fits your workflow to instantly begin tracking tasks and managing project timelines.

Frequently Asked Questions
Why are summary tasks fixed duration by default in Microsoft Project?
Summary tasks represent the roll-up of their subtasks. Their duration is automatically calculated based on the start date of the earliest subtask and the finish date of the latest subtask. Microsoft Project defaults them to Fixed Duration to prevent manual overrides from conflicting with the actual underlying data.
Can I hide summary tasks to make bulk editing easier?
Yes. Navigate to the View tab, look for the Data group, click the Filter dropdown menu, and select 'No Summary Tasks'. This will hide all summary lines so you can quickly highlight all remaining subtasks for bulk editing.
What happens if I try to assign resources to a summary task?
Assigning resources to summary tasks is strongly discouraged in MS Project. It can lead to severe over-allocations, tracking issues, and calculation errors. Resources should always be assigned strictly to the individual subtasks where the actual work occurs.