Fix Microsoft Project Inactive Tasks Not Showing Strikethrough

Bushra ParveenBushra Parveen Sep 30, 2026 869 views

Question details

The user needs to restore the strikethrough and dimmed text formatting for inactive tasks in Microsoft Project.

How to Fix Microsoft Project Inactive Tasks Not Showing Strikethrough
Product
Microsoft Project
Device & OS
not provided
Scenario
Marking tasks as inactive within the Gantt Chart view of a project.
Observed behavior
The Gantt chart bar turns from blue to white, but the task text does not appear dimmed and lacks the expected strikethrough formatting.
Before you start

Before modifying your view settings or exporting files, ensure you save a backup copy of your current Microsoft Project file, as resetting views may remove customized formatting.

Solution 1Recommended

Reset the Gantt Chart View to Default Settings

This is the most effective solution to fix corrupted view settings that prevent strikethrough formatting on inactive tasks from displaying properly.

Microsoft Project relies on specific view settings to display formatting changes. When these settings become corrupted or are accidentally altered, default formatting behaviors like the strikethrough effect on inactive tasks may stop working.

1
Access the View Menu

Navigate to the Gantt Chart view menu in your Microsoft Project ribbon.

2
Reset to Default

Select the 'Reset to Default' option from the dropdown or view settings menu.

3
Confirm the Action

Confirm the reset action when prompted. Check your task list to see if the strikethrough formatting has been restored to the inactive tasks.

Reset the Gantt Chart View to Default Settings
Free Microsoft Office alternative

Manage Projects Seamlessly with WPS Spreadsheet

While Microsoft Project is powerful, it can sometimes experience view corruption and formatting bugs. If you need a reliable and straightforward tool for project management, WPS Office provides a lightweight, highly compatible alternative. You can easily manage project timelines and tasks using the built-in Gantt chart templates in WPS Spreadsheet.

  1. 1. Download WPS Office: Install WPS Office Free from the official website and launch the application.
  2. 2. Open a Project Template: Open WPS Spreadsheet, navigate to the Template library, and search for 'Gantt Chart' to find ready-to-use project tracking sheets.
  3. 3. Track Your Tasks: Input your tasks, assign statuses, and easily track progress without worrying about complex software formatting corruptions.
Free, lightweight, and easy-to-use complete Office suiteHighly compatible with Microsoft Office formats (XLSX, DOCX, PPTX)Abundant free Gantt chart and project tracking templatesFamiliar tabbed interface ensures a seamless migration
microsoft office alternative - wps office

Frequently Asked Questions

Why do inactive tasks in Microsoft Project not show a strikethrough?

This usually happens due to a corrupted Gantt Chart view or when custom text styles override the default formatting for inactive tasks in the project file.

How do I mark a task as inactive in MS Project?

Select the task you want to deactivate, navigate to the Task tab on the ribbon, and click the 'Inactivate' button located in the Schedule group.

Will resetting the Gantt Chart view delete my project data?

No. Resetting the view only restores the default layout and formatting settings. Your project tasks, resources, dependencies, and scheduling data will remain completely intact.

Can I manually apply strikethrough formatting to tasks instead?

Yes. You can manually apply it by selecting the task row, right-clicking to choose 'Font', and then checking the 'Strikethrough' box under the Effects section.