Fix Microsoft Project Tasks Splitting After Changing Duration
Question details
The user needs to resolve an issue where changing the duration of a linked task causes downstream tasks to remain in place and appear split.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Modifying the duration of linked tasks in a project schedule.
- Observed behavior
- Downstream tasks fail to shift dynamically and instead appear split, even when no constraints, progress, or baselines are intentionally assigned.
Verify whether the affected downstream tasks are set to 'Auto Scheduled' rather than 'Manually Scheduled', as manual tasks will not shift automatically when dependencies change.
Disable the 'Split in-progress tasks' Option
Adjusting the global schedule options can prevent tasks with hidden progress or minor tracking data from splitting unexpectedly when upstream changes occur.
Microsoft Project allows tasks to split automatically if they have an actual start date or partial progress recorded. Disabling this option forces the software to handle duration changes without breaking the task bar.
Click on 'File' in the top ribbon, then select 'Options' at the bottom of the menu.
In the Project Options dialog box, click on the 'Schedule' tab located on the left-hand panel.
Scroll down to the section labeled 'Scheduling options for this project'.
Find the checkbox for 'Split in-progress tasks'. Uncheck this box and click 'OK' to apply the changes.
Verify Task Progress and Actual Start Values
Tasks that have accidentally logged progress or an Actual Start date will split instead of shifting entirely when upstream tasks are modified.
Manage Your Project Documents with WPS Office
While specialized tools like Microsoft Project handle complex dependency scheduling, WPS Office is the perfect companion for managing project reports, budget spreadsheets, and status presentations. It's a lightweight, free alternative to Microsoft Office that offers seamless file compatibility and intuitive templates.
- 1. Download WPS Office: Visit the official WPS website and download the free installation package for your operating system.
- 2. Install the Software: Run the downloaded installer and follow the simple on-screen instructions to complete the setup.
- 3. Access Project Templates: Open WPS Spreadsheet, navigate to the template library, and search for 'Project Plan' or 'Gantt Chart' to start organizing your tasks immediately.

Frequently Asked Questions
Why do my MS Project tasks split automatically?
This usually happens when the 'Split in-progress tasks' setting is enabled in your schedule options, or when a task has an 'Actual Start' date or a percentage of progress logged. Project splits the task to account for the work that has already been completed.
How do I ensure tasks move together when linked in MS Project?
First, select the tasks and link them using the chain icon on the Task tab. More importantly, ensure the downstream tasks are set to 'Auto Scheduled'. Manually scheduled tasks will remain pinned to their dates regardless of upstream changes.
What is the difference between Auto Schedule and Manually Schedule?
Auto Schedule calculates and updates task dates automatically based on dependencies, constraints, calendars, and resource assignments. Manually Scheduled tasks ignore dependencies and remain exactly where you place them on the timeline.