How to Display Week Numbers or Days on Microsoft Project Timeline

Huma Ashraf ChHuma Ashraf Ch Nov 2, 2026 869 views

Question details

The user wants to configure Microsoft Project to display specific week numbers and day numbers on the project timeline and Gantt chart.

How to Display Week Numbers or Days on the Microsoft Project Timeline
Product
Microsoft Project
Device & OS
not provided
Scenario
Customizing the timeline and Gantt chart view to show specific time increments (weeks and days) counting from the project start date.
Observed behavior
The user needs to display specific time units, noting that modifying the Gantt Chart timescale does not automatically update the visual Timeline bar above it.
Before you start

Ensure you have your Microsoft Project file open in the Gantt Chart view before adjusting the timescale settings.

Solution 1Recommended

Configure the Gantt Chart Timescale for Weeks and Days

Adjust the middle and bottom tiers of the Gantt chart timescale to show week and day numbers starting from the project start date.

Microsoft Project allows you to customize up to three tiers of your timescale. To display both weeks and days, you will need to utilize the Middle Tier and Bottom Tier settings.

1
Apply Gantt Chart View

Open your project file and ensure the Gantt Chart view is active on your screen.

2
Open Timescale Settings

Double-click the timescale bar located at the top of the Gantt Chart pane to open the Timescale dialog box.

3
Configure the Middle Tier (Weeks)

Go to the Middle Tier tab. Select 'Weeks' as the unit, set Count to 1, and choose the label format 'Week 1, Week 2, ... (From Start)'.

4
Configure the Bottom Tier (Days)

Switch to the Bottom Tier tab. Select 'Days' as the unit, set Count to 1, and select the label format 'D1, D2, D3, ... (From Start)'.

5
Apply Changes

Click OK to save and apply the new timescale format to your Gantt chart view.

Configure the Gantt Chart Timescale for Weeks and Days
Experiment with Labels: You can try other available unit and label combinations in the Timescale dialog box to find the exact display format that works best for your team's tracking needs.
Free Microsoft Office alternative

Manage Your Projects Easily with WPS Office

While Microsoft Project requires specific and costly licenses, WPS Office provides a free, lightweight, and comprehensive suite for your daily documentation and tracking needs. You can easily create beautiful project timelines and Gantt charts using free, ready-made templates in WPS Spreadsheet.

  1. 1. Download and Install: Get WPS Office for free from the official website and install it on your computer.
  2. 2. Open WPS Spreadsheet: Launch the application and open a new spreadsheet document.
  3. 3. Use Timeline Templates: Click on the Templates section, search for 'Project Timeline' or 'Gantt Chart', and apply a free template to start tracking your tasks immediately.
Free and lightweight Office suite for everyday tasksFully compatible with Microsoft Excel, Word, and PowerPoint formatsRich library of free Gantt chart and project timeline templatesFamiliar user interface for a seamless transition
microsoft office alternative - wps office

Frequently Asked Questions

Why doesn't my Timeline bar change when I update the Gantt chart timescale?

In Microsoft Project, the Timeline bar and the Gantt chart timescale operate independently. Updating the timescale on the Gantt chart will not automatically change the visual Timeline at the top. You must configure the Timeline bar separately by clicking on it and using the Timeline Format tab on the ribbon.

How do I show continuous week numbers instead of specific calendar dates?

Double-click the timescale bar, select the Middle Tier tab, set your unit to 'Weeks', and choose the label format 'Week 1, Week 2, ... (From Start)'. This will display continuous weekly numbering starting exactly from your project's kickoff date rather than calendar dates.

Can I show both weeks and days simultaneously on the Gantt chart?

Yes. You can use a multi-tier timescale to achieve this. Set the Middle Tier to display 'Weeks' and the Bottom Tier to display 'Days' within the Timescale settings dialog box. This allows you to view broader weekly summaries along with specific daily details at the same time.