How to Exclude Weekends and Holidays in Excel Gantt Planner
Question details
The user needs to configure an Excel Gantt Project Planner template to exclude weekends and company holidays from the project timeline.

- Product
- Microsoft Excel
- Device & OS
- not provided
- Scenario
- Managing project schedules and task durations using the default Gantt Project Planner template.
- Observed behavior
- The default Excel Gantt template treats weekends and holidays as standard working days, failing to calculate accurate task end dates based strictly on working hours.
Check if your project timeline strictly requires automated calculation of non-working days, as modifying the default Excel template manually can be highly complex and time-consuming.
Use Microsoft Project for Advanced Scheduling
Switch to specialized project management software like Microsoft Project, which natively supports project calendars and non-working days.
The default Gantt Project Planner template in Excel is not designed to handle complex project calendars with custom non-working times. Using dedicated scheduling software is the most efficient solution.
Open Microsoft Project and start a new project file or import your existing schedule data.
Navigate to the Project tab on the top ribbon and select 'Change Working Time' to configure your base calendar.
In the Exceptions tab, enter the dates for your company holidays. The software will automatically skip these dates and weekends when calculating task durations.

Create a Custom Gantt Chart Using the WORKDAY Function
If you must use a spreadsheet, build a custom schedule from scratch using Excel's WORKDAY function instead of relying on the default Gantt template.
Manage Project Schedules Effectively with WPS Office
Handling advanced project schedules in default spreadsheet templates can be frustrating. WPS Office provides a free, highly compatible alternative to Microsoft Office. With robust support for advanced functions like WORKDAY and a vast library of free professional Gantt chart templates, WPS Spreadsheet makes project management simple and cost-effective.
- 1. Download and Install: Get WPS Office for free from the official website and install it on your device.
- 2. Open WPS Spreadsheet: Launch the application and open your existing Excel schedule or start a new document.
- 3. Explore Templates: Navigate to the 'Templates' section and search for 'Gantt' to find professionally designed project planners.

Frequently Asked Questions
Why doesn't the default Excel Gantt template exclude weekends automatically?
The default Gantt Project Planner in Excel relies on basic conditional formatting and simple addition for date calculations. It lacks the complex underlying logical framework required to recognize and skip non-working days dynamically.
Can I use the NETWORKDAYS function to calculate project duration?
Yes, the NETWORKDAYS function in Excel calculates the total number of working days between a start date and an end date, automatically excluding weekends and any holidays you specify in a custom cell range.
Is there a free alternative to Microsoft Project for making Gantt charts?
Yes, you can use free spreadsheet alternatives like WPS Office, which offers advanced date calculation functions and a rich library of free Gantt chart templates to manage tasks effectively without the cost of premium project software.