Automatically Populate an Excel Schedule from Multiple Project Sheets

John WilsonJohn Wilson Nov 18, 2026 868 views

Question details

Automatically list projects active on each schedule date using data from two project worksheets.

Automatically Populate an Excel Schedule from Multiple Project Sheets
Product
Microsoft Excel
Device & OS
not provided
Scenario
A schedule needs to show each active project's name, crew, estimator, and total for every date.
Observed behavior
The desired schedule updates as project dates and details change.
Before you start

Make sure both project sheets use the same column names and contain real Excel dates for Start Date and Completion Date. Check that the schedule dates are also stored as dates, not text.

Solution 1Recommended

Combine the project sheets with Power Query and filter by date

Use this approach to maintain one combined project list and return active projects for a selected schedule date.

The examples assume both source sheets have columns named Project, Crew, Estimator, Start Date, Completion Date, and Total. FILTER requires a version of Excel that supports dynamic arrays.

Formula results recalculate when the combined table or schedule date changes. Changes on the original sheets appear after the Power Query data is refreshed.

1
Create source tables

On each project sheet, select the data and choose Insert > Table. Confirm that the tables have matching headers.

2
Create queries

Select a cell in each table and choose Data > From Table/Range. In Power Query, use Close & Load To and select Only Create Connection for each query.

3
Append the sheets

Choose Data > Get Data > Combine Queries > Append, select the two project queries, and load the result to a worksheet table. On the Table Design tab, name the resulting table Projects.

4
List active projects

Enter a schedule date in A2. In an empty area, enter =FILTER(Projects,(Projects[Start Date]<=A2)*(Projects[Completion Date]>=A2),"No active projects"). The result includes all six source columns for projects active on that date.

5
Calculate the date total

In a separate cell, enter =SUMIFS(Projects[Total],Projects[Start Date],"<="&A2,Projects[Completion Date],">="&A2) to sum the totals of projects active on the date in A2. Use a separate output area for each schedule date so spilled results do not overlap.

6
Refresh source changes

After editing either project sheet, choose Data > Refresh All. To refresh when the workbook opens, enable Refresh data when opening the file in the query's connection properties.

Combine the project sheets with Power Query and filter by date
Weekly totals: Define the weekly calculation before summing: adding daily totals counts a project once for every active day, while summing projects that overlap a week counts each project once.
Build your schedule in WPS

List active projects with WPS Spreadsheet

In a version of WPS Spreadsheet that supports FILTER and spilled results, filter each project sheet by a schedule date and calculate a combined daily total.

  1. 1. Open the workbook: Open the Excel workbook in WPS Spreadsheet. On Projects 1 and Projects 2, arrange columns A through F as Project, Crew, Estimator, Start Date, Completion Date, and Total.
  2. 2. Set a schedule date: On the schedule sheet, enter a real date in B1 and leave two separate output areas clear for the filtered results.
  3. 3. Filter both project sheets: In A3, enter =FILTER('Projects 1'!A2:F1000,('Projects 1'!D2:D1000<=$B$1)*('Projects 1'!E2:E1000>=$B$1),"No active projects"). In H3, enter the same formula with both references to 'Projects 1' changed to 'Projects 2'. Adjust row 1000 if the source lists grow.
  4. 4. Add the daily total: In a cell outside both output areas, add two SUMIFS calculations: =SUMIFS('Projects 1'!F2:F1000,'Projects 1'!D2:D1000,"<="&B1,'Projects 1'!E2:E1000,">="&B1)+SUMIFS('Projects 2'!F2:F1000,'Projects 2'!D2:D1000,"<="&B1,'Projects 2'!E2:E1000,">="&B1).
Display projects active on a selected schedule dateCalculate a combined total from both project sheetsOpen and save Microsoft Excel XLSX filesWork in a familiar spreadsheet interface
microsoft office alternative - wps office

Frequently Asked Questions

Does the schedule include a project on its start and completion dates?

Yes. The formulas use Start Date <= the schedule date and Completion Date >= the schedule date, so both boundary dates are included.

Why don't changes on the project sheets appear immediately?

If you combined the sheets with Power Query, choose Data > Refresh All after editing the source tables. You can also enable refresh when opening the file in the connection properties.

Why does FILTER show a spill error?

Clear any cells blocking the formula's output area. Leave enough space for all matching rows and columns, and place results for different dates in separate areas.

How can I total projects that overlap a week without counting them each day?

For a week starting in A2 and ending in B2, use =SUMIFS(Projects[Total],Projects[Start Date],"<="&B2,Projects[Completion Date],">="&A2). This counts each matching project once.