Calculate Estimated Days Remaining from Project Completion Percentage in WPS Spreadsheet

Huma Ashraf ChHuma Ashraf Ch Nov 13, 2026 868 views

Question details

The user needs to estimate a project end date from a start date and the current completion percentage using WPS Spreadsheet.

Calculate Estimated Days Remaining from Project Completion Percentage in WPS Spreadsheet
Product
WPS Spreadsheet
Device & OS
not provided
Scenario
The user tracks a project by its start date and current completion percentage and needs to estimate the project end date.
Observed behavior
The desired result is an estimated completion date in a worksheet cell that recalculates when the completion percentage changes.
Before you start

Check that your start date is a recognized date value and your completion percentage is formatted as a percentage. Avoid using the formula when the completion percentage is zero, or wrap it with an IF condition to prevent a #DIV/0! error.

Solution 1Recommended

Calculate the Estimated Completion Date with a Date Formula

Use this formula when you have a start date and a non-zero completion percentage and want an estimated project end date in WPS Spreadsheet.

The formula treats the completion percentage as progress over elapsed time. It projects the total duration from the start date to today and adds that duration to the start date.

1
Select the result cell

Click an empty cell, such as E100, where you want the estimated completion date to appear.

2
Enter the formula

Type =D100+100%/C100*(TODAY()-D100) and press Enter, where D100 is the start date and C100 is the completion percentage.

3
Format the result as a date

Select the formula cell, click the Home tab, open the Number Format drop-down, and choose Short Date or Long Date.

Calculate the Estimated Completion Date with a Date Formula
Zero percentage handling: If C100 is zero or empty, the formula returns a #DIV/0! error. Use =IF(C100=0,"",D100+100%/C100*(TODAY()-D100)) to return a blank instead of an error.
WPS Spreadsheet solution

Calculate Project Completion Dates in WPS Spreadsheet

Use WPS Spreadsheet to estimate the remaining days and project end date with a simple formula. The workbook recalculates the estimate automatically as you update the completion percentage.

  1. 1. Open your workbook: Launch WPS Office and open the workbook that contains the project start date and completion percentage.
  2. 2. Enter the completion date formula: Click an empty cell, type =D100+100%/C100*(TODAY()-D100), replace D100 and C100 with your actual cell references, and press Enter.
  3. 3. Format the result as a date: Select the formula cell, click Home, open the Number Format drop-down, and choose Short Date or Long Date.
  4. 4. Update the percentage: Change the completion percentage in C100; WPS Spreadsheet recalculates the estimated completion date immediately.
Returns an estimated project end date from a start date and completion percentageCompatible with Microsoft Excel .xlsx workbooks and formulasFree, lightweight WPS Office spreadsheet toolFamiliar Excel-like interface for easy migrationAutomatic recalculation when the percentage changes
microsoft office alternative - wps office

Frequently Asked Questions

Why does the estimated completion date change when the completion percentage changes?

The formula uses TODAY()-D100 as elapsed time and divides it by the completion percentage. When C100 changes, the projected total duration changes, so the estimated end date recalculates automatically in WPS Spreadsheet.

What should I do if my percentage cell is zero?

Do not use the basic formula with a zero percentage because it can cause a #DIV/0! error. Instead, use =IF(C100=0,"",D100+100%/C100*(TODAY()-D100)) and replace D100 and C100 with your actual cell references.

Can I use this project completion formula in Microsoft Excel?

Yes, the formula syntax is compatible with Microsoft Excel and WPS Spreadsheet. Both support TODAY(), percentage division, and date arithmetic, so the same .xlsx workbook can be opened in either application.

How do I format the estimated completion date as a date?

Select the formula cell, click the Home tab, open the Number Format drop-down, and choose Short Date or Long Date. The formula result then displays as a date instead of a serial number.