Export Microsoft Project Resource Usage by Task and Day to Excel
Question details
Export resource assignments and daily work by task from Microsoft Project to Excel, including additional fields where possible.

- Product
- Microsoft Project and Microsoft Excel
- Device & OS
- not provided
- Scenario
- The user wants to analyze resource allocation by task and day in an Excel report and filter it by a field such as Team Name.
- Observed behavior
- Visual Reports can create a time-phased Excel PivotTable, but the available templates and field list may not include every project field.
Open the project in Microsoft Project and check the Resource Usage view to confirm that assignments and work values are present. Identify where Team Name is stored, such as in a resource, task, or project field, before choosing a reporting method.
Create an Excel Visual Report for assignment usage
Use a Visual Report when the available assignment and time fields meet your reporting needs.
In Microsoft Project, select View > Resource Usage and check the resources, assigned tasks, and work values you want to report.
Select Report > Visual Reports, then look for an Excel template under Assignment Usage that provides the resource, task, and work information you need.
In the Visual Reports dialog, set the level of usage data to Days, if available, and select View to generate the report in Excel.
In Excel, use the PivotTable Field List to arrange available resource and task fields in rows, time in columns, and work in Values. Check whether the required fields and daily detail are present.

Convert the OLAP PivotTable to formulas
Use this option to customize the Excel layout when the Visual Report already contains the data you need.
Build a custom export with the missing fields
Use a custom report when the Visual Report data source cannot provide Team Name or another required field.
Review exported resource usage in WPS Spreadsheet
WPS Office is a free, lightweight alternative with a familiar interface for working with exported spreadsheets. Open compatible Excel files in WPS Spreadsheet to review resource usage after exporting it from Microsoft Project.

Frequently Asked Questions
Why is Team Name missing from the Excel PivotTable Field List?
The Visual Report field list is limited to fields included in its data source. Editing the template does not necessarily add a Project field that the source does not expose.
How do I show daily work in a Visual Report?
In Project, open Report > Visual Reports and set the usage-data level to Days if that option is available. Generate the report and place the available time and work fields in the Excel PivotTable.
Can I filter the report by Resource Group?
Resource Group may be available as a displayed property in some reports, but it may not be available as a filterable PivotTable field. Check the generated report's Field List.
Will converting the PivotTable to formulas expose Team Name?
No. Excel's PivotTable Analyze > OLAP Tools > Convert to Formulas changes the report layout but does not add fields missing from the data source.
Can I change the date format in the Visual Report PivotTable?
Date labels in the Visual Report may be determined by the Project data source. Check the generated report's time fields and Excel formatting options, but the PivotTable may not allow the desired label format.