How to Create a Floating Stacked Bar Chart with Project Dates in WPS Office Spreadsheet

Tauseeq MagsiTauseeq Magsi Nov 13, 2026 869 views

Question details

How to create a floating stacked bar chart in WPS Office Spreadsheet to visualize project durations against actual start dates.

How to Create a Floating Stacked Bar Chart with Project Dates in WPS Office Spreadsheet
Product
WPS Office Spreadsheet
Device & OS
not provided
Scenario
The user is preparing a project timeline and needs each task duration to appear as a floating bar positioned by its real start date.
Observed behavior
The chart should display project names on one axis and real dates on the other; the start date series acts as an invisible spacer so only duration bars are visible.
Before you start

Organize your data in three columns—Project, Start Date, and Duration—and format the Start Date column as real date values so the chart axis can be scaled correctly.

Solution 1Recommended

Create the floating stacked bar chart with an invisible Start Date series

Use this method when you have tasks with start dates and durations and want the bars to begin at their actual dates on a date axis.

In a stacked bar chart, the first series shifts the second series to the right. By making the Start Date series transparent, only the Duration series remains visible and starts at the correct date position.

1
Prepare the source data in WPS Spreadsheet

Enter project names, start dates, and duration values in three adjacent columns and apply a Date format to the Start Date cells.

2
Insert a stacked bar chart

Select the data range, go to the Insert tab, click Chart, choose Bar, and then select Stacked Bar.

3
Set the series order

Right-click the chart, choose Select Data, and make sure Start Date is the first series and Duration is the second series.

4
Make the Start Date series invisible

Right-click the Start Date bars in the chart, choose Format Data Series, and set Fill to No Fill and Border to No Line.

5
Format the horizontal date axis

Right-click the horizontal axis, choose Format Axis, set Axis Type to Date, and adjust the minimum and maximum bounds to cover the required quarters or project range.

Create the floating stacked bar chart with an invisible Start Date series
Chart ready: The visible bars now float at each task’s real start date and extend by its duration.
WPS Spreadsheet chart tutorial

Create a Project Date Floating Stacked Bar Chart in WPS Office Spreadsheet

Use WPS Office Spreadsheet to build a floating stacked bar chart by making the Start Date series transparent and formatting the axis as real dates, so your project timeline is clear and editable.

  1. 1. Open WPS Office Spreadsheet: Enter the project name, start date, and duration data in separate columns.
  2. 2. Insert the chart: Select the data and insert a Stacked Bar chart from the Insert tab.
  3. 3. Hide the Start Date series: Format the Start Date series with No Fill and No Line so only duration bars remain visible.
  4. 4. Set the date axis: Format the horizontal axis as Date and set the minimum and maximum bounds to your project range.
  5. 5. Save the file: Save or export the workbook as .xlsx to share with Excel users.
Uses the same stacked bar chart workflow as Excel for a smooth learning curveStart Date series can be made transparent without extra formulas or helper columnsOpen, edit, and save .xlsx files with full Microsoft Excel format compatibilityFree timeline visualization tool with the familiar Office ribbon and chart toolsShare project charts in WPS Office without losing formatting
microsoft office alternative - wps office

Frequently Asked Questions

Why does my floating bar chart still show all bars starting at zero?

The Start Date series is probably still visible or is not set as the first series. In Select Data, make sure Start Date is the first series and format it with No Fill and No Line so it only creates the offset.

Can I use real dates as the horizontal axis in a floating stacked bar chart?

Yes. In WPS Office Spreadsheet, right-click the horizontal axis, choose Format Axis, set Axis Type to Date, and adjust the minimum and maximum bounds to the required date range.

What data layout should I use for a floating stacked bar chart?

Use three columns: project or task name, start date, and duration. The start date column must contain date values and the duration column should contain numeric values such as days.

How do I add visible duration labels to the floating bars?

Right-click the Duration series, choose Add Data Labels, and then format the labels to show values or task names as needed.

Will this chart work if I save the file as .xlsx and open it in Excel?

Yes. WPS Office Spreadsheet supports Excel-compatible charts, so the stacked bar chart with an invisible Start Date series and formatted date axis remains editable in Microsoft Excel.