How to Flag Missing or Invalid Dates and Calculate Date Differences in WPS Office Spreadsheet
Question details
The user needs an Excel-compatible formula in WPS Office Spreadsheet that displays a warning when a date is missing or when the date difference is negative, and calculates the difference for valid date pairs. Text dates must be converted to real Excel date values first.

- Product
- WPS Office Spreadsheet
- Device & OS
- not provided
- Scenario
- The user is working with a start date and an end date and needs to calculate the difference only when the end date exists and is not earlier than the start date.
- Observed behavior
- The formula returns incorrect results or warnings because some date entries are stored as text rather than real Excel date values.
Before writing the formula, select the date columns and confirm that they contain real Excel date values rather than text. Check the number format on the Home tab or use =ISNUMBER(cell), and convert text dates before applying date arithmetic.
Use IF and OR to Flag Missing or Invalid Dates and Calculate Date Differences
Best for a single warning message when the end date is blank or earlier than the start date, while returning the day difference for valid date pairs.
Excel stores real dates as serial numbers, so subtracting one date from another works only when both cells are actual date values. Text dates can make the formula return #VALUE! or the wrong result.
The formula below checks the end date first, then calculates D2-C2 only when neither the missing-date condition nor the negative-difference condition is true.
If any date cells are stored as text, select those cells, go to Data > Text to Columns, click Next twice, choose Date, and then click Finish to convert them into real Excel dates.
In the first result cell, such as E2, enter =IF(OR(D2="",D2-C2<0),"Requires contract award / actual date to be amended",D2-C2).
Drag the fill handle from the first result cell down to apply the formula to the remaining rows.
Select the result column, open the Home tab, and choose General or Number from the number format menu so the returned date difference displays correctly.

Use NETWORKDAYS to Calculate Working Days After Validating Dates
Use this when the result should exclude weekends and optionally holidays instead of counting all calendar days.
Use WPS Office Spreadsheet to Flag Invalid Dates and Calculate Date Differences
Open the workbook in WPS Office Spreadsheet and apply the Excel-compatible IF/OR formula to show a warning for missing or invalid dates. WPS Office provides the same date serial number system, function syntax, and ribbon tools as Microsoft Excel, so the workbook can be edited and shared without losing formulas.
- 1. Open the workbook in WPS Office Spreadsheet: Open the .xlsx or .xls file in WPS Office Spreadsheet and select the worksheet that contains the date columns.
- 2. Convert text dates to real dates: Select any date cells that are stored as text, go to Data > Text to Columns, click Next twice, choose Date, and click Finish.
- 3. Enter the formula: In the result cell, enter =IF(OR(D2="",D2-C2<0),"Requires contract award / actual date to be amended",D2-C2).
- 4. Fill and format the result column: Drag the fill handle down and set the result cells to General or Number from the Home tab.

Frequently Asked Questions
Why does my date difference formula show a warning even though the end date looks correct?
The end date is probably stored as text instead of a real Excel date. In WPS Office Spreadsheet, select the cell and check the number format on the Home tab, or use =ISNUMBER(D2). Real dates return TRUE; text dates return FALSE. Convert text dates with Data > Text to Columns before using =IF(OR(D2="",D2-C2<0),"Requires contract award / actual date to be amended",D2-C2).
How do I convert text dates into real dates in WPS Office Spreadsheet?
Select the date cells, go to Data > Text to Columns, click Next twice, choose Date, and click Finish. You can also use =DATEVALUE(D2) in a helper column, then paste the values back over the original entries.
Can the formula calculate working days instead of calendar days?
Yes. Use NETWORKDAYS inside the same validation formula: =IF(OR(D2="",D2-C2<0),"Requires contract award / actual date to be amended",NETWORKDAYS(C2,D2)). Add a holiday range as the third argument if needed.
What does #VALUE! mean in a date difference formula?
A #VALUE! error usually means at least one cell in the subtraction is text, not a real date. Convert the text date to a real Excel date and re-enter or recalculate the formula.
Does this Excel date formula work in WPS Office?
Yes. WPS Office Spreadsheet supports the same IF, OR, and NETWORKDAYS functions and the same Excel date serial number system, so the formula behaves the same when opening and saving .xlsx workbooks.