Move Excel Dates to the Next Working Day After Weekends and Holidays
Question details
Automatically adjust schedule dates that fall on weekends or listed holidays to the next working day.
- Product
- Microsoft Excel
- Device & OS
- not provided
- Scenario
- A schedule contains dates that need to be checked against weekends and a holiday list.
- Observed behavior
- Valid working dates remain unchanged, while weekend and holiday dates move forward to the next eligible working day.
Place the schedule dates in column A and the holiday dates in G2:G12, or adjust the formulas to match your worksheet. Make sure both ranges contain actual Excel dates rather than text.
Use WORKDAY to adjust dates around weekends and holidays
Use this formula to keep valid working dates unchanged and move other dates to the next working day.
WORKDAY treats Saturday and Sunday as weekends and skips the dates in the holiday range.
In an empty cell such as B2, enter =WORKDAY(A2-1,1,$G$2:$G$12). Replace A2 and the holiday range if your dates are in different cells.
Select B2 and drag its fill handle down alongside the dates in column A. The dollar signs keep the holiday range fixed.
If the results appear as numbers, select the result cells and choose Home > Number Format > Short Date or another date format.

Adjust schedule dates with WORKDAY in WPS Spreadsheets
Use the WORKDAY function in WPS Spreadsheets to move weekend and holiday dates forward while leaving valid working dates unchanged.
- 1. Open your schedule: Open WPS Spreadsheets and use Open to select your Excel workbook.
- 2. Prepare the holiday list: Enter actual holiday dates in G2:G12, or identify the range that already contains them.
- 3. Enter the formula: In B2, enter =WORKDAY(A2-1,1,$G$2:$G$12), adjusting the references to match your sheet.
- 4. Apply and format the results: Drag the fill handle down from B2, then select the results and use the Home tab's number format controls to display them as dates.

Frequently Asked Questions
How do I keep a date unchanged if it is already a working day?
Use =WORKDAY(A2-1,1,$G$2:$G$12). Subtracting one day allows WORKDAY to return the original date when it is not a weekend or listed holiday.
How do I move every date to a later working day?
Enter =WORKDAY(A2,1,$G$2:$G$12). This returns the first working day after A2, even when A2 is already a working day.
What happens if a holiday is followed by a weekend or another holiday?
WORKDAY skips all consecutive weekend days and dates in the specified holiday range until it finds an eligible working day.
Why does the formula show a number instead of a date?
Excel stores dates as serial numbers. Select the result cells and choose Home > Number Format > Short Date to display them as dates.




