The user wants to configure backward scheduling from a specific project finish date and apply advanced task dependencies like Start-to-Start and Finish-to-Finish.

Product
Microsoft Project for the Web
Device & OS
not provided
Scenario
Setting up complex project timelines and mapping out overlapping task dependencies.
Observed behavior
Project for the Web does not support backward scheduling and only allows standard Finish-to-Start task dependencies.
Before you start

Confirm whether you are currently using Project for the Web or the Microsoft Project desktop application, as advanced scheduling capabilities are exclusive to the desktop version.

Solution 1Recommended

Use Microsoft Project Desktop Application for Advanced Scheduling

Switching to the Microsoft Project desktop application allows you to schedule backward from a finish date and utilize advanced dependency types (SS, FF, SF).

Project for the Web is a lightweight, cloud-based tool designed for simple project management. It intentionally omits complex scheduling engines to maintain simplicity. To access robust scheduling features, you must migrate your workflow to the full Microsoft Project desktop client.

1
Open Microsoft Project Desktop

Launch the Microsoft Project Professional desktop application and open a new or existing project file.

2
Enable Backward Scheduling

Navigate to the 'Project' tab on the ribbon and click on 'Project Information'. In the dialog box, change the 'Schedule from' dropdown option to 'Project Finish Date', then enter your target completion date.

3
Set Advanced Task Dependencies

Double-click on any task to open the 'Task Information' window. Go to the 'Predecessors' tab.

4
Select Dependency Type

In the 'Type' column, select your required dependency, such as Start-to-Start (SS) or Finish-to-Finish (FF), and click 'OK' to apply.

Use Microsoft Project Desktop Application for Advanced Scheduling
Feature Availability: If your organization only provides Project Plan 1 licenses, you may need to request an upgrade to Project Plan 3 or 5 to access the desktop application.
Free Microsoft Office alternative

Manage Project Timelines Effortlessly with WPS Office

While Microsoft Project offers advanced scheduling, it can be costly and overly complex for standard tasks. For straightforward project tracking, Gantt charts, and timeline management, WPS Office provides free, easily customizable templates in its Spreadsheet application. It delivers a familiar interface, lightweight performance, and seamless compatibility with standard Office files.

  1. 1. Open WPS Spreadsheets: Launch WPS Office on your device and click on 'Spreadsheets' to start a new workspace.
  2. 2. Access the Template Library: Click on 'New' and navigate to the 'Template' section to browse available document formats.
  3. 3. Search for Project Templates: Type 'Project Management' or 'Gantt Chart' in the search bar to find ready-to-use timeline templates.
  4. 4. Customize Your Timeline: Download your chosen template and easily customize the tasks, start dates, and durations to track your project efficiently.
Access a rich library of free project management and Gantt chart templates.Fully compatible with Microsoft Excel (.xlsx) formats for easy team sharing.Lightweight software that runs smoothly on Windows, Mac, and Linux.Free alternative to expensive and complex project management suites.
microsoft office alternative - wps office

Frequently Asked Questions

Why can't I schedule from a finish date in Project for the Web?

Project for the Web is designed for simplified, modern project management and currently only supports forward scheduling from a start date. For backward scheduling, Microsoft requires users to use the traditional Microsoft Project desktop application.

Does Project for the Web support Start-to-Start dependencies?

No, Project for the Web currently only supports standard Finish-to-Start (FS) task dependencies. Advanced dependency types like Start-to-Start (SS) and Finish-to-Finish (FF) are only available in the desktop version.

How do I transition from Project for the Web to the desktop app?

Depending on your Office 365 setup, you can connect your environment via Project Online or export your basic task lists to Excel, and then import them into the Microsoft Project Professional desktop client to begin applying advanced scheduling logic.