How to Manage Task Dates, Dependencies, and Resources in Microsoft Project
Question details
The user needs guidance on handling task durations, updating completion percentages accurately, managing employee vacations, and understanding the differences between actual, scheduled, and baseline dates in Microsoft Project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Taking over a manually managed project schedule and transitioning it to automatic scheduling using task dependencies and resource calendars.
- Observed behavior
- Currently, extending task times alters the percentage complete inaccurately, employee vacations disrupt the timeline, and the lack of task dependencies requires manual date adjustments.
Before modifying task dependencies or resource calendars, save a baseline of your current project file so you can easily compare your new automated schedule against the original manual plan.
Update Remaining Duration to Extend Task End Dates
Use this method when a task requires more calendar time to complete, but you want the percent complete to remain accurate based on the actual effort already spent.
In Microsoft Project, percent complete is generally tied to elapsed duration. If you manually increase the total duration, the percentage drops because the ratio of completed time to total time changes. Adjusting the remaining work solves this issue.
Click on the specific task in your Gantt Chart view that needs a deadline extension.
Navigate to the Task tab on the ribbon, find the Schedule group, and click on 'Update Tasks'.
Instead of changing the overall Duration field, update the 'Remaining Duration' or 'Remaining Work' fields to reflect the extra time needed.

Handle Employee Vacations Using Split Tasks or Calendars
Pause tasks during employee vacations or non-working days to ensure accurate automatic scheduling without inflating the required task work hours.
Utilize Scheduled, Actual, and Baseline Dates
Properly classify your dates to track project progress, compare current forecasts against initial goals, and maintain historical accuracy.
Manage Project Timelines Easily with WPS Office
While Microsoft Project is built for complex dependency tracking, you can effectively manage task schedules, Gantt charts, and resource allocations using WPS Spreadsheet—a free, lightweight alternative to Microsoft Excel with full Office compatibility and built-in project management templates.
- 1. Download and Install: Download WPS Office for free from the official website and install it on your device.
- 2. Access Templates: Open WPS Spreadsheet, go to the Homepage, and click on 'Templates'.
- 3. Create a Project Tracker: Search for 'Project Management' or 'Gantt Chart' to find and apply a ready-made template to organize your tasks and dates.

Frequently Asked Questions
Why does my percentage complete change when I increase a task's duration?
In Microsoft Project, percentage complete is generally calculated based on elapsed duration versus total duration. If you manually increase the total duration without adding corresponding completed work, the mathematical ratio of progress drops, lowering the percentage complete.
What is the difference between Scheduled dates and Actual dates?
Scheduled dates are dynamic forecasts that Project calculates automatically based on current progress and task dependencies. Actual dates are historical records that you manually input to state exactly when a task began or finished.
How do I compare my current automated schedule to my original manual plan?
You must save a Baseline before making changes. Go to Project > Set Baseline. This copies your original schedule into Baseline fields, allowing you to view a Variance table later to see how much your dates have shifted from the original plan.