How to Manage Task Dates, Dependencies, and Resources in Microsoft Project

Natalie TaylorNatalie Taylor Oct 16, 2026 870 views

Question details

The user needs guidance on handling task durations, updating completion percentages accurately, managing employee vacations, and understanding the differences between actual, scheduled, and baseline dates in Microsoft Project.

How to Manage Task Dates, Dependencies, and Resources in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Taking over a manually managed project schedule and transitioning it to automatic scheduling using task dependencies and resource calendars.
Observed behavior
Currently, extending task times alters the percentage complete inaccurately, employee vacations disrupt the timeline, and the lack of task dependencies requires manual date adjustments.
Before you start

Before modifying task dependencies or resource calendars, save a baseline of your current project file so you can easily compare your new automated schedule against the original manual plan.

Solution 1Recommended

Update Remaining Duration to Extend Task End Dates

Use this method when a task requires more calendar time to complete, but you want the percent complete to remain accurate based on the actual effort already spent.

In Microsoft Project, percent complete is generally tied to elapsed duration. If you manually increase the total duration, the percentage drops because the ratio of completed time to total time changes. Adjusting the remaining work solves this issue.

1
Select the task

Click on the specific task in your Gantt Chart view that needs a deadline extension.

2
Open the Update Tasks dialog

Navigate to the Task tab on the ribbon, find the Schedule group, and click on 'Update Tasks'.

3
Modify remaining time

Instead of changing the overall Duration field, update the 'Remaining Duration' or 'Remaining Work' fields to reflect the extra time needed.

Update Remaining Duration to Extend Task End Dates
Fixed-Work Tasks: If you set the task type to 'Fixed Work', the total effort remains constant while the finish date moves, ensuring your percent complete stays perfectly intact.
Free Microsoft Office alternative

Manage Project Timelines Easily with WPS Office

While Microsoft Project is built for complex dependency tracking, you can effectively manage task schedules, Gantt charts, and resource allocations using WPS Spreadsheet—a free, lightweight alternative to Microsoft Excel with full Office compatibility and built-in project management templates.

  1. 1. Download and Install: Download WPS Office for free from the official website and install it on your device.
  2. 2. Access Templates: Open WPS Spreadsheet, go to the Homepage, and click on 'Templates'.
  3. 3. Create a Project Tracker: Search for 'Project Management' or 'Gantt Chart' to find and apply a ready-made template to organize your tasks and dates.
Fully compatible with Microsoft Excel (.xlsx) formats for seamless schedule sharing.Includes built-in, easy-to-use Gantt chart and project tracker templates.Free and lightweight with a familiar, user-friendly interface.Cross-platform support allows you to track project progress on PC, Mac, and mobile devices.
QA img-9

Frequently Asked Questions

Why does my percentage complete change when I increase a task's duration?

In Microsoft Project, percentage complete is generally calculated based on elapsed duration versus total duration. If you manually increase the total duration without adding corresponding completed work, the mathematical ratio of progress drops, lowering the percentage complete.

What is the difference between Scheduled dates and Actual dates?

Scheduled dates are dynamic forecasts that Project calculates automatically based on current progress and task dependencies. Actual dates are historical records that you manually input to state exactly when a task began or finished.

How do I compare my current automated schedule to my original manual plan?

You must save a Baseline before making changes. Go to Project > Set Baseline. This copies your original schedule into Baseline fields, allowing you to view a Variance table later to see how much your dates have shifted from the original plan.