Others

Microsoft Project: Update Baselines for Changed Tasks and Resources

Muhammad TalhaMuhammad Talha Nov 25, 2026 869 views

Question details

The user needs to track cost and earned-value changes after modifying tasks or resources and review assignments for selected tasks.

Update Microsoft Project Baselines for Changed Tasks and Resources
Product
Microsoft Project 2013 and 2016
Device & OS
not provided
Scenario
A project schedule has changed, and project managers need an appropriate baseline and a way to review resource assignments.
Observed behavior
Resource replacements can change costs and variances, while the user needs a practical way to see resources and work for selected tasks.
Before you start

Identify whether the schedule has changed enough to require a new project-wide baseline or whether only specific tasks need updating. Confirm which baseline your organization uses for earned-value reporting before replacing it.

Solution 1Recommended

Update the baseline for the entire project or selected tasks

Use a project-wide baseline for a substantially revised schedule, or baseline selected new or affected tasks for smaller changes.

A baseline captures planned task, resource, and assignment costs for comparison with current values. Replacing baseline values changes the reference used for variance and earned-value analysis.

1
Choose the scope

Open the project and review the changed tasks in the Gantt Chart. For a partial update, select the new or affected task rows.

2
Open baseline settings

On the Project tab, select Set Baseline, then choose Set Baseline.

3
Save the baseline

Choose the baseline to update. Select Entire project for a substantially revised schedule or Selected tasks for a partial update, then click OK.

4
Check the results

Add the Baseline Cost, Cost, and Cost Variance columns to a task view to compare the saved baseline with current costs.

Update the baseline for the entire project or selected tasks
Preserve a comparison point: If you need to retain the existing baseline, consider saving the revised plan in an additional baseline, such as Baseline1. Confirm which baseline is used for earned-value calculations before changing reporting settings.
Free Microsoft Office alternative

Review project cost data in WPS Spreadsheets

WPS Office is a free, lightweight alternative for working with exported project cost data in a familiar spreadsheet interface. Open compatible Excel files to review and share tables, though WPS does not update Microsoft Project baselines.

Review exported task and resource cost tables in a spreadsheetOpen and edit Microsoft Excel formats such as XLSXUse a familiar interface for an easy transition from Microsoft OfficeWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Should I rebaseline the whole project after adding a task?

Not necessarily. If the existing plan remains valid, select the new task and use Project > Set Baseline > Set Baseline with Selected tasks. A substantially revised schedule may warrant an entire-project baseline.

What happens to cost variance when I replace a resource?

Project recalculates the assignment and task costs using the replacement resource's rates and displays the difference against the baseline. Check Cost Variance in Task Usage and record the reason for the replacement in Task Information > Notes.

Can I keep the original baseline when saving a revised plan?

Yes. In Project > Set Baseline > Set Baseline, you can choose an additional baseline such as Baseline1. Check which baseline your earned-value reporting uses before changing it.

How can I see resources assigned to tasks under a summary task?

Open View > Task Usage, identify the relevant subtasks, and use the Task Name AutoFilter to narrow the view. Expand the displayed task rows to see their resource assignments and work.

Can WPS Office change a Microsoft Project baseline?

No. Update the baseline in Microsoft Project. WPS Spreadsheets can instead help you review project data exported to a compatible Excel file.