Microsoft Project: Update Baselines for Changed Tasks and Resources
Question details
The user needs to track cost and earned-value changes after modifying tasks or resources and review assignments for selected tasks.

- Product
- Microsoft Project 2013 and 2016
- Device & OS
- not provided
- Scenario
- A project schedule has changed, and project managers need an appropriate baseline and a way to review resource assignments.
- Observed behavior
- Resource replacements can change costs and variances, while the user needs a practical way to see resources and work for selected tasks.
Identify whether the schedule has changed enough to require a new project-wide baseline or whether only specific tasks need updating. Confirm which baseline your organization uses for earned-value reporting before replacing it.
Update the baseline for the entire project or selected tasks
Use a project-wide baseline for a substantially revised schedule, or baseline selected new or affected tasks for smaller changes.
A baseline captures planned task, resource, and assignment costs for comparison with current values. Replacing baseline values changes the reference used for variance and earned-value analysis.
Open the project and review the changed tasks in the Gantt Chart. For a partial update, select the new or affected task rows.
On the Project tab, select Set Baseline, then choose Set Baseline.
Choose the baseline to update. Select Entire project for a substantially revised schedule or Selected tasks for a partial update, then click OK.
Add the Baseline Cost, Cost, and Cost Variance columns to a task view to compare the saved baseline with current costs.

Review resource cost changes and document replacements
Use cost fields and task notes to explain variances when a resource is replaced.
Filter Task Usage to review resources for selected tasks
Use the Task Usage view when you need to inspect resource assignments and work for particular tasks or subtasks.
Review project cost data in WPS Spreadsheets
WPS Office is a free, lightweight alternative for working with exported project cost data in a familiar spreadsheet interface. Open compatible Excel files to review and share tables, though WPS does not update Microsoft Project baselines.

Frequently Asked Questions
Should I rebaseline the whole project after adding a task?
Not necessarily. If the existing plan remains valid, select the new task and use Project > Set Baseline > Set Baseline with Selected tasks. A substantially revised schedule may warrant an entire-project baseline.
What happens to cost variance when I replace a resource?
Project recalculates the assignment and task costs using the replacement resource's rates and displays the difference against the baseline. Check Cost Variance in Task Usage and record the reason for the replacement in Task Information > Notes.
Can I keep the original baseline when saving a revised plan?
Yes. In Project > Set Baseline > Set Baseline, you can choose an additional baseline such as Baseline1. Check which baseline your earned-value reporting uses before changing it.
How can I see resources assigned to tasks under a summary task?
Open View > Task Usage, identify the relevant subtasks, and use the Task Name AutoFilter to narrow the view. Expand the displayed task rows to see their resource assignments and work.
Can WPS Office change a Microsoft Project baseline?
No. Update the baseline in Microsoft Project. WPS Spreadsheets can instead help you review project data exported to a compatible Excel file.