Fix Incorrect Baseline Cost for Selected Tasks in Microsoft Project
Question details
Review and correct baseline cost rollup when saving a baseline for selected tasks.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A baseline is saved for selected tasks rather than the entire project.
- Observed behavior
- Baseline costs may not reflect the expected task or summary values, depending on the rollup options selected.
Identify the tasks and baseline you intend to update, and decide whether their baseline values should roll up to summary tasks. Updating an existing baseline replaces the saved baseline values for the selected tasks.
Review Rollup Options When Saving the Selected Tasks Baseline
Use this method when baseline costs at the task and summary levels do not match the intended rollup.
Open the project in Microsoft Project and select the task rows whose baseline values you want to update.
On the Project tab, select Set Baseline, then choose Set Baseline. Select the baseline you want to update and choose Selected tasks.
Under Roll up baselines, select To all summary tasks if the selected tasks' updated baseline values should roll up to their summary tasks. Select From subtasks into selected summary task(s) if selected summary tasks should be updated from their subtasks. Choose the options that match your intended summary behavior, then select OK.
In the task table, right-click a column heading, choose Insert Column, and add Baseline Cost. Compare the values for the selected tasks and their summary tasks.

Review Project Cost Data in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for working with spreadsheet data. Open compatible Microsoft Office files to review exported project costs, though WPS does not fix Microsoft Project baseline rollup settings.

Frequently Asked Questions
Why does a summary task show an unexpected baseline cost?
When you save a baseline for selected tasks, the summary value depends on the rollup options chosen in Project > Set Baseline > Set Baseline. Review those options and compare the Baseline Cost column for the tasks and their summaries.
How do I roll selected task baselines up to their summary tasks?
Select the task rows, open Project > Set Baseline > Set Baseline, and choose Selected tasks. Under Roll up baselines, select To all summary tasks before confirming.
How can I see the saved baseline cost for a task?
Right-click a column heading in the task table, choose Insert Column, and select Baseline Cost. Check both the task rows and their summary rows.
Will saving a baseline for selected tasks change the original values?
Yes. Saving to an existing baseline replaces the stored baseline values for the selected tasks, so check the baseline name and task selection in the Set Baseline dialog before confirming.