How to Create a Summary View for Selected Tasks in Microsoft Project
Question details
The user wants to generate a high-level schedule displaying only selected tasks from a master project without having to create a separate file or display every subtask.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Generating a customized high-level project report or view for stakeholders.
- Observed behavior
- The default views show all subtasks or require manual creation of separate project files to isolate specific main activities.
Ensure you open the master project with read/write access so that your new custom filters and view configurations can be saved correctly.
Use the Marked Column and Custom Filters
This is the most efficient way to dynamically display only the tasks you want to highlight in your master project.
By leveraging the built-in 'Marked' column, you can flag specific tasks and then apply a custom filter to hide everything else. This prevents the need to maintain multiple copies of the same project file.
Right-click on any column header in your Gantt Chart view, select 'Insert Column', and choose 'Marked' from the dropdown list.
Go through your task list and change the value in the Marked column to 'Yes' for every task you want to appear in your high-level summary.
Navigate to the View tab, open the Filter dropdown, and select 'New Filter'. Name it something recognizable like 'Summary View Filter'.
Set the Field Name to 'Marked', the Test to 'equals', and the Value to 'Yes'. Check the box for 'Show related summary tasks' if you want to maintain the hierarchy structure, then save and apply the filter.

Create a Dedicated Custom View
Ideal if you need to frequently switch between the detailed master schedule and the high-level summary without manually reapplying filters.
Manage Project Schedules Easily with WPS Office
If you don't need the heavy complexity of Microsoft Project, WPS Spreadsheet offers an excellent, lightweight alternative. You can easily create Gantt charts, manage task summaries, and filter high-level schedules using familiar spreadsheet tools—all for free.
- 1. Open a Project Template: Launch WPS Spreadsheet, navigate to the template library, and search for 'Gantt Chart' or 'Project Schedule'.
- 2. Input Task Data: Enter your task names, start dates, and durations into the pre-formatted spreadsheet.
- 3. Filter High-Level Tasks: Use the Data tab to apply AutoFilters to your columns, allowing you to instantly hide subtasks and display only summary milestones.

Frequently Asked Questions
Can I export this summary view to a PDF for stakeholder reporting?
Yes, once your custom filter is applied, you can go to File > Print or File > Export to save the filtered high-level Gantt chart directly as a PDF document.
What is the difference between a Flag field and the Marked field in Microsoft Project?
The Marked field is a built-in Yes/No field natively designed for quick highlighting. Flag1 through Flag20 are customizable fields that you can define and rename for more complex, specific filtering rules across different views.
How do I ensure the parent tasks stay visible when filtering out subtasks?
When setting up your custom filter, ensure you check the box labeled 'Show related summary tasks'. This forces Microsoft Project to display the parent summary tasks even if they do not directly meet the filter criteria.