Fix Missing Summary Tasks in a Microsoft Project Grouped Gantt View
Question details
The user needs to display summary tasks and their bars in a grouped Microsoft Project Gantt view.

- Product
- Microsoft Project 2013
- Device & OS
- not provided
- Scenario
- A project schedule is displayed in a grouped Gantt view with Always Roll Up Gantt Bars enabled.
- Observed behavior
- Some summary tasks or bars disappear in the grouped view despite the rollup setting. Changing Flag1 made a summary task appear in one view but not in the grouped view.
Open the affected project in Microsoft Project and note the active view and grouping. Identify which summary task and outline level are missing so you can compare them with an ungrouped Gantt view.
Check Rollup Fields and Summary Bar Styles
Use this approach to identify rollup or formatting settings that may prevent summary bars from appearing.
Rollup controls whether a task's bar can be rolled up to a summary bar. The relevant setting may need to be checked at more than one outline level, and a grouped view may display the result differently.
In the Gantt Chart view, right-click a column heading, select Insert Column, and choose Rollup.
Expand the task outline and inspect the Rollup value for the affected tasks and summary tasks at each relevant level. Set Rollup to Yes where the bar should roll up, then collapse the levels to check the result.
Double-click the relevant summary task, open its Task Information dialog, and check its bar rollup settings on the General tab, including Always Roll Up Gantt Bars.
On the Gantt Chart Format tab, open Bar Styles and check the Summary and other applicable bar styles. Review their appearance and any task conditions, such as a Flag1 condition, that could exclude the affected summary task.

Compare the Grouped and Ungrouped Gantt Views
Use this comparison to determine whether grouping is responsible for the missing summary task or bar.
Review Exported Project Data in WPS Spreadsheets
WPS Office is a free, lightweight alternative with a familiar interface for working with Office files. Export project data to an Excel workbook in Microsoft Project, then open it in WPS Spreadsheets for an easy transition to spreadsheet-based review. WPS does not fix Microsoft Project's grouped Gantt display.

Frequently Asked Questions
Why are summary bars missing even though Always Roll Up Gantt Bars is enabled?
The Rollup field at individual outline levels, bar style conditions, or grouping behavior may affect the display. Insert the Rollup column and check the relevant tasks, then inspect Bar Styles on the Gantt Chart Format tab.
How do I check the Rollup value for a task?
In Gantt Chart view, right-click a column heading, select Insert Column, and choose Rollup. Review the values for the affected tasks and summary levels.
Can Flag1 affect whether a summary bar appears?
It can if a bar style uses Flag1 as a display condition. Open Gantt Chart Format > Bar Styles and check the conditions for the relevant bar style before changing the flag.
What if the summary task appears only when grouping is removed?
Select View > Group By > No Group to use the ungrouped view when reviewing summary bars. If the grouped view still omits the summary after the settings are checked, a project-specific workaround may be necessary.