Others

Fix Missing Summary Tasks in a Microsoft Project Grouped Gantt View

Rana GarciaRana Garcia Nov 20, 2026 869 views

Question details

The user needs to display summary tasks and their bars in a grouped Microsoft Project Gantt view.

Fix Missing Summary Tasks in a Microsoft Project Grouped Gantt View
Product
Microsoft Project 2013
Device & OS
not provided
Scenario
A project schedule is displayed in a grouped Gantt view with Always Roll Up Gantt Bars enabled.
Observed behavior
Some summary tasks or bars disappear in the grouped view despite the rollup setting. Changing Flag1 made a summary task appear in one view but not in the grouped view.
Before you start

Open the affected project in Microsoft Project and note the active view and grouping. Identify which summary task and outline level are missing so you can compare them with an ungrouped Gantt view.

Solution 1Recommended

Check Rollup Fields and Summary Bar Styles

Use this approach to identify rollup or formatting settings that may prevent summary bars from appearing.

Rollup controls whether a task's bar can be rolled up to a summary bar. The relevant setting may need to be checked at more than one outline level, and a grouped view may display the result differently.

1
Show the Rollup field

In the Gantt Chart view, right-click a column heading, select Insert Column, and choose Rollup.

2
Review outline levels

Expand the task outline and inspect the Rollup value for the affected tasks and summary tasks at each relevant level. Set Rollup to Yes where the bar should roll up, then collapse the levels to check the result.

3
Check summary settings

Double-click the relevant summary task, open its Task Information dialog, and check its bar rollup settings on the General tab, including Always Roll Up Gantt Bars.

4
Inspect bar styles

On the Gantt Chart Format tab, open Bar Styles and check the Summary and other applicable bar styles. Review their appearance and any task conditions, such as a Flag1 condition, that could exclude the affected summary task.

Check Rollup Fields and Summary Bar Styles
Grouped views may differ: Setting Rollup to Yes can help when an outline level is collapsed, but it may not restore a summary bar in a grouped view.
Free Microsoft Office alternative

Review Exported Project Data in WPS Spreadsheets

WPS Office is a free, lightweight alternative with a familiar interface for working with Office files. Export project data to an Excel workbook in Microsoft Project, then open it in WPS Spreadsheets for an easy transition to spreadsheet-based review. WPS does not fix Microsoft Project's grouped Gantt display.

Review exported task and summary data in a spreadsheetOpen and edit Microsoft Excel XLSX workbooksUse a familiar spreadsheet interfaceWork with a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why are summary bars missing even though Always Roll Up Gantt Bars is enabled?

The Rollup field at individual outline levels, bar style conditions, or grouping behavior may affect the display. Insert the Rollup column and check the relevant tasks, then inspect Bar Styles on the Gantt Chart Format tab.

How do I check the Rollup value for a task?

In Gantt Chart view, right-click a column heading, select Insert Column, and choose Rollup. Review the values for the affected tasks and summary levels.

Can Flag1 affect whether a summary bar appears?

It can if a bar style uses Flag1 as a display condition. Open Gantt Chart Format > Bar Styles and check the conditions for the relevant bar style before changing the flag.

What if the summary task appears only when grouping is removed?

Select View > Group By > No Group to use the ungrouped view when reviewing summary bars. If the grouped view still omits the summary after the settings are checked, a project-specific workaround may be necessary.