Fix Missing Tasks and Incorrect Dates in Microsoft Project Gantt Charts
Question details
The user needs to locate task bars and verify dates displayed in a Microsoft Project Gantt chart.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Tasks have start dates, finish dates, and predecessors, but the user cannot find their bars or sees them under an unexpected year.
- Observed behavior
- Some task bars are outside the visible chart area or hidden, while others appear under a year that does not match the expected dates.
Open the project in Gantt Chart view and identify a task whose bar is missing or appears under the wrong year. Note its displayed start and finish dates so you can compare them with the chart.
Scroll to the Task and Check the Gantt Timescale
Use this method when a task bar may be outside the visible date range or the chart labels are misleading.
In Gantt Chart view, click the task row in the table on the left.
Choose Task > Editing > Scroll to Task. Project moves the chart to the selected task's scheduled date.
Double-click the timescale above the chart to open its settings. Review the tier units and date labels, and adjust them so the month and year are clear.
If the timescale uses fiscal-year numbering, review the fiscal-year options in File > Options > Schedule and the timescale settings. A fiscal-year label can differ from the calendar year without changing the task's scheduled date.

Compare the Standard Start and Finish Fields
Use this check when the dates in the table do not seem to match the Gantt bar.
Review Gantt Bar Styles and Task Visibility
Use this method if scrolling to the task does not reveal its bar.
Use WPS Office for Project Tables and Reports
WPS Office is a free, lightweight alternative for working with everyday Office documents. Its familiar interface and Microsoft Office format compatibility make it easy to move project tables and reports into your workflow. It does not fix Microsoft Project Gantt chart settings.

Frequently Asked Questions
Why can't I see a task bar even though the task has dates?
The bar may be outside the visible timescale or hidden by a bar style. Select the task and choose Task > Editing > Scroll to Task, then check Bar Styles if the bar still does not appear.
Why does a task appear under a different year?
Check the timescale labels and fiscal-year settings first. Also compare the standard Start and Finish columns with the bar style's From and To fields; the table or bar may be using baseline or custom dates.
How do I show the standard task dates?
In Gantt Chart view, right-click a task-table column heading, choose Insert Column, and add Start and Finish. These fields show the current scheduled dates rather than baseline or custom dates.
Does a fiscal-year label change the task's scheduled date?
No. Fiscal-year numbering can change how a year is labeled on the timescale, but it does not by itself change the task's Start or Finish date. Review File > Options > Schedule and the timescale settings.