Fix Incorrect Summary Task Dates When Importing P6 XML to Project
Question details
The user needs to correct summary task dates in Microsoft Project that fail to align with their respective subtask dates after importing an XML file exported from Oracle Primavera P6.

- Product
- Microsoft Project, Oracle Primavera P6
- Device & OS
- not provided
- Scenario
- Importing a project schedule via an XML file exported from Oracle Primavera P6 into Microsoft Project.
- Observed behavior
- Summary task dates in Microsoft Project do not reflect the dates of their subtasks, even with automatic scheduling and calculation enabled.
Verify your current Microsoft Project version to rule out recent application update bugs, and double-check that automatic calculation is enabled before troubleshooting the XML import.
Remove Duplicate Predecessor Relationships in Primavera P6
Microsoft Project cannot correctly process duplicate predecessor relationships. Removing them in P6 before exporting the XML file resolves the summary task date calculation errors.
When importing an XML file from Oracle Primavera P6, duplicate predecessor relationships can cause Microsoft Project to miscalculate summary task dates. Microsoft Project generally does not accept multiple dependency types (like having both a Start-to-Start and a Finish-to-Finish dependency) between the exact same tasks.
Attempting to fix this by saving the file as an MPP and converting it back to XML will not work, as the underlying relationship data remains flawed. The issue must be corrected directly within the source P6 file.
Launch Oracle Primavera P6 and open the specific project you intend to export.
Review the task dependencies and identify any tasks that have duplicate predecessors assigned (e.g., both 1960SS and 1960FF linking the same two tasks).
Delete the duplicate or conflicting relationships so that only one valid, driving predecessor dependency remains for those tasks.
Navigate to 'File' > 'Export', select 'XML' as the format, and export the corrected project schedule.
Open Microsoft Project, go to 'File' > 'Open', select the newly generated XML file, and verify that the summary task dates now accurately reflect the subtasks.

Manage Project Documentation with WPS Office
While Microsoft Project handles complex P6 XML imports, you can rely on WPS Office for all your project reporting, budgeting, and presentation needs. WPS Office offers a free, lightweight suite that seamlessly integrates with your existing workflows.
- 1. Download the software: Visit the official WPS Office website and download the free installer for your operating system.
- 2. Install WPS Office: Run the setup file and follow the on-screen instructions to complete the lightweight installation.
- 3. Open project files: Launch the application to instantly view, edit, and create Word, Excel, and PowerPoint compatible project documents.

Frequently Asked Questions
Why do summary task dates not match subtasks in Microsoft Project?
This typically happens if automatic scheduling is turned off, or if imported data contains conflicting dependency rules, such as duplicate predecessors that Microsoft Project cannot calculate properly.
Can Microsoft Project handle multiple predecessor relationships between the same tasks?
Generally, no. Microsoft Project does not handle duplicate predecessor relationships well (e.g., having both Start-to-Start and Finish-to-Finish dependencies for the same tasks). It is best practice to keep only the primary driving relationship.
How do I fix P6 XML import calculation errors in Microsoft Project?
To fix import calculation errors, you should first clean up the schedule in Primavera P6 by removing duplicate relationships, then re-export the XML file, and import it fresh into Microsoft Project.
Does saving the imported file as an MPP and re-importing the XML fix the dates?
No, saving as MPP and converting back to XML retains the underlying data errors, such as duplicate predecessors, which cause the calculation issue. The root cause must be resolved in Oracle Primavera P6 before exporting.