Fix Microsoft Project Doubling Duration and Work During Excel Import
Question details
The user needs to prevent Microsoft Project from automatically doubling task duration and work values when importing project data with multiple resources from Excel.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Importing a task list containing tasks with two or more assigned resources from an Excel worksheet into Microsoft Project.
- Observed behavior
- Duration and work values are unexpectedly doubled upon import. For example, a task with 10 hours of duration and 20 hours of work changes to 20 hours of duration and 40 hours of work.
Before proceeding, ensure you have a backup copy of your original Excel source file and verify that you have access to modify the default schedule options in your Microsoft Project file.
Change Default Task Type to Fixed Work
Adjusting the task type to Fixed Work prevents Microsoft Project from multiplying the total work hours by the number of resources assigned during the import process.
By default, Microsoft Project sets tasks to 'Fixed Units'. When multiple resources are imported at 100% allocation, the software assumes each resource is working the full duration, thereby multiplying the total work and duration. Using 'Fixed Work' locks the total intended work hours regardless of how many resources are assigned.
Launch Microsoft Project, go to the 'File' tab in the ribbon, and select 'Options' at the bottom left. Then, click on the 'Schedule' tab in the Project Options dialog box.
Scroll down to the 'Scheduling options for this project' section. Locate the 'Default task type' dropdown menu and change it from 'Fixed Units' to 'Fixed Work'.
Save the settings and run the Excel import wizard again. The imported work and duration values will now remain constant even with multiple resources assigned.
Exclude Summary Tasks from Excel Import
Avoid importing duration and work values for summary tasks, as Microsoft Project's built-in calculation engine handles these automatically based on subtasks.
Use a Separate Assignment Worksheet
When resources require different assignment percentages (units), a standard flat-file import often ignores them. A separate assignment worksheet ensures accurate distribution.
Manage Your Project Data Seamlessly with WPS Office
While specialized tools like Microsoft Project can be overly complex and strict with data imports, WPS Spreadsheet offers a lightweight, flexible, and completely free alternative for tracking tasks, durations, and resources using intuitive project management templates.
- 1. Download WPS Office: Install WPS Office Free on your device to access the full suite of spreadsheet and document tools.
- 2. Explore Project Templates: Open WPS Spreadsheet and browse the built-in template library for 'Gantt Chart' or 'Project Management' to start tracking your tasks.
- 3. Import Excel Tasks: Open your existing Excel task lists directly in WPS Spreadsheet to manage your resources and work hours without forced, complex recalculations.

Frequently Asked Questions
Why does Microsoft Project change my work hours when I assign multiple resources?
By default, Microsoft Project uses 'Fixed Units' for new tasks. When you import a task and assign multiple resources, the software assumes each resource works the full duration at 100% capacity, effectively multiplying the total work hours by the number of resources. Changing the task type to 'Fixed Work' resolves this.
How do I display the Work column in the Gantt Chart view?
To see the total work hours alongside your tasks, right-click on any existing column header in the Gantt Chart view, select 'Insert Column', type 'Work' in the search field, and select it to add the column to your current view.
Can I import task duration directly for summary tasks?
It is not recommended to import duration or work values for summary tasks. Microsoft Project is designed to automatically calculate summary task values by rolling up the durations and work hours of their underlying subtasks.
Why does the task type revert to Fixed Units when reopening my file?
If you only changed the task type for existing tasks rather than the project default, new imports will still default to Fixed Units. To fix this permanently for the file, you must navigate to File > Options > Schedule and change the 'Default task type' to Fixed Work.