How to Fix Summary Task Constraints After Asta Powerproject Export
Question details
Users need to correct summary task constraints that are incorrectly modified after exporting an MPP file from Asta Powerproject into Microsoft Project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Importing or opening an MPP project file in Microsoft Project that was generated by an Asta Powerproject export.
- Observed behavior
- Summary tasks default to a 'Start No Earlier Than' constraint instead of the standard 'As Soon As Possible' constraint, which restricts dynamic schedule calculations.
Before modifying task constraints in bulk, ensure you save a backup copy of your imported MPP file so you can easily revert changes if the project schedule shifts unexpectedly.
Manually Correct Constraint Types Using the Summary Tasks Filter
This is the most direct and safest method to update all summary tasks to the correct constraint type simultaneously without affecting standard tasks.
By applying a built-in filter, you can isolate the affected summary tasks and adjust their properties in one go, avoiding the tedious process of editing them one by one.
In Microsoft Project, navigate to the 'View' tab on the top ribbon. In the 'Data' group, click the 'Filter' dropdown menu and select 'Summary Tasks' to hide all subtasks.
Click the top-left cell of the table (above the row numbers) or drag your cursor to highlight all the visible summary tasks in your project.
Right-click anywhere on the selected tasks and choose 'Information' from the context menu, or simply press 'Shift + F2' to open the Multiple Task Information dialog box.
Go to the 'Advanced' tab in the dialog box. Locate the 'Constraint type' dropdown menu, select 'As Soon As Possible', and click 'OK' to apply the change.
Return to the 'View' tab, open the 'Filter' dropdown menu again, and select '[No Filter]' or 'All Tasks' to restore your complete project view.

Automate Corrections with a VBA Macro
If you frequently import files from Asta Powerproject, using a VBA macro can instantly update all summary task constraints with a single click.
Looking for a Lightweight Alternative for Project Tracking?
While Microsoft Project handles complex MPP file formatting, WPS Office is the perfect free and lightweight alternative for managing project tracking sheets, reports, and team presentations. It provides excellent compatibility with Microsoft Office formats, allowing you to seamlessly handle Word, Excel, and PowerPoint files without expensive subscription fees.
- 1. Download and Install WPS Office: Visit the official WPS website to download the free suite and install it on your device.
- 2. Open WPS Spreadsheet: Launch WPS Office and open WPS Spreadsheet to start managing your project data.
- 3. Use Built-in Templates: Search the template library for Gantt charts or project tracking templates to instantly organize your workflows.

Frequently Asked Questions
Why do summary task constraints change when exporting from Asta Powerproject?
Different project management software tools handle task scheduling algorithms differently. Asta Powerproject's export mechanism translates its internal scheduling logic into Microsoft Project's MPP format, which often applies a 'Start No Earlier Than' constraint to summary tasks to preserve specific date boundaries.
Can I prevent this constraint issue during the Asta export process?
Currently, this is a known behavior associated with the MPP export function in Asta Powerproject. The most reliable method is to perform a post-import cleanup in Microsoft Project to fix the constraints.
What happens if I leave the constraints as 'Start No Earlier Than'?
Leaving the constraints as 'Start No Earlier Than' on summary tasks can severely restrict your schedule's flexibility. It prevents Microsoft Project from automatically bringing forward summary task dates when predecessor tasks are completed ahead of schedule.