How to Fix As Late As Possible Constraints Delaying Tasks in Microsoft Project
Question details
The user needs to prevent the As Late As Possible (ALAP) constraint on procurement tasks from unexpectedly delaying linked production tasks.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Scheduling project phases, specifically linking procurement tasks to subsequent production tasks.
- Observed behavior
- Applying an ALAP constraint to procurement disrupts the intended project schedule by unnecessarily delaying downstream production tasks.
Before modifying task constraints, save a baseline of your current project schedule so you can compare changes and easily revert if needed.
Use As Soon As Possible (ASAP) Scheduling with Critical Path
Remove the ALAP constraint and switch to ASAP scheduling. Use total slack and late dates to manually identify how long procurement can wait without delaying the project.
The As Late As Possible (ALAP) constraint forces a task to consume all its available slack. In critical path scheduling, this often creates unintended bottlenecks because any minor delay in procurement will immediately delay the linked production task.
Instead of forcing ALAP, it is best practice to let the scheduling engine run As Soon As Possible (ASAP). You can then monitor the 'Total Slack' column to see exactly how many days procurement can be safely postponed.
Double-click the specific procurement task that is causing the delay to open the Task Information dialog box.
Navigate to the 'Advanced' tab. Click on the 'Constraint type' drop-down menu and change it from 'As Late As Possible' to 'As Soon As Possible'.
Ensure the 'Constraint date' field is cleared or set to 'NA', then click 'OK' to apply the new scheduling behavior.
Switch your view to the Detail Gantt, or right-click the column headers in your Gantt Chart view to insert the 'Total Slack' column. Use this number to determine the latest safe start date for procurement.

Manage Project Timelines Easily with WPS Office
If complex scheduling algorithms in Microsoft Project are causing friction, consider managing everyday timelines, budgets, and tasks using the free Gantt chart templates available in WPS Spreadsheet. It offers a straightforward, highly compatible alternative for team project tracking.
- 1. Download and Install: Visit the official WPS Office website to download the suite for free.
- 2. Open the Template Library: Launch WPS Spreadsheet, click on 'New', and browse the built-in template library.
- 3. Find a Project Template: Search for 'Gantt' or 'Project' to find an intuitive timeline tracker.
- 4. Input Your Schedule: Fill in your task names, start dates, and durations to generate a visual project schedule without worrying about complex constraint errors.

Frequently Asked Questions
What exactly does the As Late As Possible (ALAP) constraint do?
The ALAP constraint automatically schedules a task to finish at the latest possible date without delaying the project's overall completion. However, this consumes all available float (slack) for the task, making the schedule rigid.
Why does my production task move when I set procurement to ALAP?
If procurement is linked to production as a predecessor, setting procurement to ALAP pushes it right up against the start of the production task. Any minor scheduling shift then immediately pushes the production task outward.
How can I see late start and late finish dates in MS Project?
You can view these dates by adding the 'Late Start' and 'Late Finish' columns to your Gantt Chart view. Right-click any column header, select 'Insert Column', and type the name of the respective field.