Fix Microsoft Project Successor Tasks Not Rescheduling Automatically

Camila MilosovichCamila Milosovich Oct 7, 2026 869 views

Question details

The user needs to make successor tasks reschedule automatically when predecessor tasks change in Microsoft Project.

How to Fix Microsoft Project Successor Tasks Not Rescheduling Automatically
Product
Microsoft Project
Device & OS
not provided
Scenario
Updating project schedules or reusing project templates with pre-existing dependencies and task constraints.
Observed behavior
Successor tasks do not move when earlier tasks are rescheduled, despite being set to automatic scheduling and having established dependencies.
Before you start

Before adjusting task constraints, ensure that your project is set to Auto Schedule and verify you haven't manually typed in start dates, which can inadvertently lock tasks in place.

Solution 1Recommended

Change Task Constraints to 'As Soon As Possible'

Removing rigid date constraints allows Microsoft Project's task relationships to dynamically drive the project schedule.

When you manually enter a start date or use a template from a previous project, Microsoft Project often applies a 'Start No Earlier Than' constraint. This prevents tasks from shifting earlier, even if their predecessors finish early.

1
Select Affected Tasks

Highlight the specific successor tasks that are not moving, or select all tasks in the project to fix them simultaneously.

2
Open Task Information

Right-click the selected tasks and choose 'Information', or click the 'Information' button on the Task ribbon.

3
Modify the Constraint

Navigate to the 'Advanced' tab in the Task Information dialog box.

4
Set to As Soon As Possible

Click the 'Constraint Type' dropdown menu, select 'As Soon As Possible', and click 'OK'.

Change Task Constraints to 'As Soon As Possible'
Bulk Editing: Selecting all tasks and changing the constraint type in one go is the fastest way to clear unintended constraints imported from project templates.
Free Microsoft Office alternative

Manage Your Projects Efficiently with WPS Office

While Microsoft Project is designed for complex scheduling, it often introduces rigid constraints and high costs. WPS Office provides a free, lightweight, and easy-to-use alternative for general project tracking, documentation, and reporting without the steep learning curve.

  1. 1. Download the Installer: Visit the official WPS Office website and click the free download button.
  2. 2. Install the Software: Run the setup file and follow the on-screen instructions to install the suite.
  3. 3. Start Managing Projects: Open WPS Spreadsheet to build your Gantt charts, task lists, and project dashboards effortlessly.
Create and track dynamic project timelines using customizable WPS Spreadsheet templates.Highly compatible with Microsoft Excel, Word, and PowerPoint file formats.Free and lightweight suite perfect for agile and everyday project management.Familiar tabbed interface ensures a seamless migration and zero learning curve.
microsoft office alternative - wps office

Frequently Asked Questions

Why do my Microsoft Project tasks have constraints I didn't set?

When you manually type a specific start or finish date into the Gantt chart columns, Microsoft Project automatically assumes you want to lock that date and applies a 'Start No Earlier Than' or 'Finish No Earlier Than' constraint.

Can I bulk edit task constraints in MS Project?

Yes. You can select multiple tasks in the Gantt Chart view, open the Task Information dialog, and change the constraint type in the Advanced tab. This will apply the new constraint setting, like 'As Soon As Possible', to all selected tasks simultaneously.

What is the difference between Auto Schedule and Manual Schedule in MS Project?

Auto Schedule calculates and updates task dates dynamically based on dependencies, constraints, and working calendars. Manual Schedule ignores these scheduling factors, freezing tasks to the exact dates you input manually.