How to Fix Microsoft Project Finish Date Not Updating Correctly
Question details
The user needs to resolve an issue where a task's finish date does not recalculate as expected after modifying the actual duration or remaining work.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Updating project schedules by changing task durations or remaining work.
- Observed behavior
- The task keeps an unexpected finish date instead of automatically updating based on the new duration or work values.
Ensure your project file is saved and temporarily change your date format to include times, which will make it easier to spot hidden scheduling discrepancies.
Verify Schedule Options and Calendar Settings
Check the global scheduling options and project calendar to ensure Microsoft Project calculates dates accurately based on your actual workweek.
Microsoft Project relies heavily on specific calendar settings and working hours to calculate finish dates. If your default 'Hours per day' setting conflicts with your project calendar, dates will not calculate as expected.
Go to File > Options > General. Under 'Project view', change the 'Date format' to an option that includes the time (e.g., 1/28/02 12:33 PM) to monitor exact finish times.
Navigate to File > Options > Schedule. Verify that the 'Hours per day' and 'Hours per week' settings correctly match your intended working schedule.
Go to Project > Project Information on the ribbon. Check that the correct 'Start date' is set and that the appropriate 'Calendar' is assigned to the project.
Click Project > Change Working Time. Review your workweek settings (such as a standard five-day or six-day workweek) and ensure there are no unintended non-working days blocking the schedule.
Adjust Task Type Settings
Ensure the individual task type is configured to allow the finish date to recalculate when duration or work changes.
Manage Project Timelines Easily with WPS Office
While Microsoft Project is dedicated to complex project management, WPS Spreadsheet provides an intuitive, lightweight alternative for tracking schedules, creating Gantt charts, and managing project milestones. As a free Office suite, it offers full compatibility with standard Office files without the steep learning curve.
- 1. Download and Install WPS Office: Download WPS Office for free from the official website and install it on your computer.
- 2. Open a Project Template: Launch WPS Spreadsheet, go to the template library, and search for 'Project Management' or 'Gantt Chart'.
- 3. Track Your Project: Input your task details, start dates, and durations to automatically generate and visualize your project timeline.

Frequently Asked Questions
Why is the finish date not moving when I increase a task's duration?
This often occurs if the task has a 'Finish No Later Than' constraint applied or if the task type is strictly set to 'Fixed Duration'. You can adjust these parameters by double-clicking the task and checking the Advanced tab.
Does changing the project calendar automatically update all task finish dates?
Yes, modifying working hours, adding holidays, or extending the workweek in 'Change Working Time' will recalculate task dates automatically, provided the tasks are set to Auto Scheduled and lack specific date constraints.
What is the difference between Auto Scheduled and Manually Scheduled tasks?
Auto Scheduled tasks have their start and finish dates dynamically calculated by the software based on dependencies, calendars, and durations. Manually Scheduled tasks require manual date entry and will not automatically recalculate when project variables change.
How can I see the exact time a task finishes?
Go to File > Options > General, and in the 'Date format' dropdown menu, choose a format that displays both the date and the time. This helps identify situations where a task finishes in the middle of a working day.