Fix Microsoft Project Finish-to-Finish Dependency Not Updating

Emma BrownEmma Brown Nov 2, 2026 869 views

Question details

The user is experiencing an issue where a successor task does not automatically move or update when a predecessor is delayed, despite having a finish-to-finish dependency applied.

How to Fix Microsoft Project Finish-to-Finish Dependency Not Updating
Product
Microsoft Project
Device & OS
not provided
Scenario
Managing project timelines and adjusting task dependencies when predecessor tasks experience delays.
Observed behavior
Even when both tasks are set to automatically schedule, the finish-to-finish dependency fails to push the successor task's dates forward in response to the predecessor's delay.
Before you start

Before adjusting advanced settings, ensure that all affected tasks are set to Auto Scheduled rather than Manually Scheduled, and verify that your project plan has a properly defined start date in the Project Information tab.

Solution 1Recommended

Enable the Split In-Progress Tasks Setting

Allowing Microsoft Project to split in-progress tasks ensures that remaining work can be delayed to satisfy dependency constraints when predecessors run late.

When tasks are partially completed but their predecessors are delayed, Microsoft Project may hold the successor task in place to prevent disrupting active work. Enabling task splitting permits the software to pause the active task and push the remaining work out, honoring the finish-to-finish dependency.

1
Open Project Options

Click on the 'File' menu at the top left of the screen and select 'Options' at the bottom of the navigation pane.

2
Navigate to Schedule Settings

In the Project Options dialog box, select the 'Schedule' tab from the left-hand menu.

3
Enable Task Splitting

Scroll down to the 'Scheduling options for this project' section. Check the box labeled 'Split in-progress tasks'.

4
Apply Changes

Click 'OK' to save your settings. The scheduling engine will recalculate and correctly push the remaining work for the successor task.

Enable the Split In-Progress Tasks Setting
Instant Recalculation: Once applied, you should immediately see the Gantt chart update, showing a split in the successor task's timeline to accommodate the predecessor's delay.
Free Microsoft Office alternative

Manage Project Schedules with WPS Spreadsheet Templates

If you do not require the heavy complexity of Microsoft Project, WPS Office serves as an excellent free alternative. You can easily manage project timelines, tasks, and dependencies using intuitive built-in Gantt chart templates in WPS Spreadsheet.

  1. 1. Download and Install: Download WPS Office for free and launch the Spreadsheet application.
  2. 2. Access Templates: Click on 'New' and navigate to the Templates library to search for 'Project Management' or 'Gantt'.
  3. 3. Customize Your Plan: Select a template and input your tasks, durations, and start dates to easily visualize your project timeline.
Highly compatible with Microsoft Excel (.xlsx) formats for easy sharing.Extensive library of free project management and Gantt chart templates.Lightweight architecture ensuring fast performance on all devices.Familiar user interface requiring zero learning curve for Office users.
microsoft office alternative - wps office

Frequently Asked Questions

What is a Finish-to-Finish (FF) dependency in project management?

A Finish-to-Finish dependency means that the successor task cannot finish until the predecessor task has finished. The two tasks do not have to finish at the same exact time, but the successor's completion is gated by the predecessor's completion.

Why does an actual start date break automatic scheduling?

When you input an actual start date or register actual work, Microsoft Project assumes the task has begun in reality. The software prioritizes real-world data, pinning the task's start date in place and overriding predictive scheduling logic.

How do I ensure all my tasks are automatically scheduled?

You can highlight all tasks in your Gantt Chart, navigate to the 'Task' tab on the top ribbon, and click 'Auto Schedule' in the Tasks group. This switches them from Manually Scheduled (pinned dates) to Auto Scheduled (dynamic dates based on dependencies).