Fix Microsoft Project Finish-to-Finish Dependency Not Updating
Question details
The user is experiencing an issue where a successor task does not automatically move or update when a predecessor is delayed, despite having a finish-to-finish dependency applied.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Managing project timelines and adjusting task dependencies when predecessor tasks experience delays.
- Observed behavior
- Even when both tasks are set to automatically schedule, the finish-to-finish dependency fails to push the successor task's dates forward in response to the predecessor's delay.
Before adjusting advanced settings, ensure that all affected tasks are set to Auto Scheduled rather than Manually Scheduled, and verify that your project plan has a properly defined start date in the Project Information tab.
Enable the Split In-Progress Tasks Setting
Allowing Microsoft Project to split in-progress tasks ensures that remaining work can be delayed to satisfy dependency constraints when predecessors run late.
When tasks are partially completed but their predecessors are delayed, Microsoft Project may hold the successor task in place to prevent disrupting active work. Enabling task splitting permits the software to pause the active task and push the remaining work out, honoring the finish-to-finish dependency.
Click on the 'File' menu at the top left of the screen and select 'Options' at the bottom of the navigation pane.
In the Project Options dialog box, select the 'Schedule' tab from the left-hand menu.
Scroll down to the 'Scheduling options for this project' section. Check the box labeled 'Split in-progress tasks'.
Click 'OK' to save your settings. The scheduling engine will recalculate and correctly push the remaining work for the successor task.

Remove Actual Start Dates from Successor Tasks
Clearing unintended actual start dates allows the automatic scheduling engine to freely adjust task timelines based on dependencies.
Manage Project Schedules with WPS Spreadsheet Templates
If you do not require the heavy complexity of Microsoft Project, WPS Office serves as an excellent free alternative. You can easily manage project timelines, tasks, and dependencies using intuitive built-in Gantt chart templates in WPS Spreadsheet.
- 1. Download and Install: Download WPS Office for free and launch the Spreadsheet application.
- 2. Access Templates: Click on 'New' and navigate to the Templates library to search for 'Project Management' or 'Gantt'.
- 3. Customize Your Plan: Select a template and input your tasks, durations, and start dates to easily visualize your project timeline.

Frequently Asked Questions
What is a Finish-to-Finish (FF) dependency in project management?
A Finish-to-Finish dependency means that the successor task cannot finish until the predecessor task has finished. The two tasks do not have to finish at the same exact time, but the successor's completion is gated by the predecessor's completion.
Why does an actual start date break automatic scheduling?
When you input an actual start date or register actual work, Microsoft Project assumes the task has begun in reality. The software prioritizes real-world data, pinning the task's start date in place and overriding predictive scheduling logic.
How do I ensure all my tasks are automatically scheduled?
You can highlight all tasks in your Gantt Chart, navigate to the 'Task' tab on the top ribbon, and click 'Auto Schedule' in the Tasks group. This switches them from Manually Scheduled (pinned dates) to Auto Scheduled (dynamic dates based on dependencies).