The user is experiencing an issue where successor task dates in Microsoft Project do not adjust automatically when the durations of predecessor tasks are changed.

How to Fix Microsoft Project Successor Dates Not Updating
Product
Microsoft Project
Device & OS
not provided
Scenario
Modifying predecessor task durations in a project schedule and expecting successor tasks to auto-adjust accordingly.
Observed behavior
Successor task dates remain static and fail to recalculate or move based on predecessor changes.
Before you start

Before modifying task constraints or links, ensure you have saved a backup copy of your project file. It is also highly recommended to switch to the Gantt Chart view so you can visually track which tasks are failing to update.

Solution 1Recommended

Identify and Remove Restrictive Task Constraints

Task constraints lock dates in place, preventing Microsoft Project from automatically rescheduling successor tasks when predecessor durations change.

When constraints like 'Must Start On' or 'Finish No Earlier Than' are applied, they override the dynamic linking of tasks. Removing these constraints allows the software's calculation engine to function normally.

1
Open Gantt Chart View

Navigate to the View tab on the ribbon and select Gantt Chart to display your task list and timeline.

2
Insert Constraint Type Column

Right-click on any column header in the task table, select 'Insert Column', type 'Constraint Type', and press Enter to add it to your view.

3
Filter for Restrictive Constraints

Click the AutoFilter drop-down arrow on the newly added Constraint Type column. Look for constraints such as 'Finish No Earlier Than', 'Must Start On', or 'Must Finish On'.

4
Change Constraint to As Soon As Possible

For the tasks that are stuck, double-click the task to open Task Information, go to the Advanced tab, and change the constraint type back to 'As Soon As Possible'.

Identify and Remove Restrictive Task Constraints
Recalculation: Once restrictive constraints are removed, the schedule should immediately recalculate and push successor dates out appropriately.
Free Microsoft Office alternative

Manage Your Projects with WPS Spreadsheet Templates

If you're looking for a simpler, more cost-effective way to track tasks and project schedules without the complexities of Microsoft Project, WPS Office provides excellent project management templates. Enjoy a free, lightweight suite with full compatibility with Microsoft Office file formats.

Free and lightweight alternative to heavy project management softwareHigh compatibility with Microsoft Excel (.xlsx) formats for easy sharingHundreds of built-in project tracking and Gantt chart templatesFamiliar, intuitive user interface for seamless onboarding
microsoft office alternative - wps office

Frequently Asked Questions

Why does Microsoft Project stop calculating dates automatically?

Microsoft Project may stop auto-calculating if the calculation mode is accidentally set to Manual, if there are restrictive constraints applied to certain tasks, or if a circular reference exists in your task dependencies causing the calculation engine to halt.

How do I know if my project has a circular reference?

Microsoft Project typically displays a warning dialog box as soon as a circular reference is created. If you bypassed it, you might notice that changes to task durations no longer affect the overall project schedule and successor dates refuse to budge.

What is the default constraint type in Microsoft Project?

For projects that are scheduled from a specific start date, the default constraint type is 'As Soon As Possible'. This setting allows tasks to be scheduled dynamically based entirely on their links and durations.

Can I force Microsoft Project to recalculate my schedule?

Yes. If your calculation mode is set to manual or seems stuck, you can force a recalculation by pressing F9 on your keyboard, or by navigating to the Project tab and clicking 'Calculate Project' in the Calculate group.