Fix Project Task Dates Not Updating for Zero-Day Tasks
Question details
Users need to fix an issue where zero-day tasks (milestones) do not automatically update their dates when the project calendar is changed.

- Product
- Project Online
- Device & OS
- not provided
- Scenario
- Modifying the overall project calendar and expecting all task schedules to adjust accordingly.
- Observed behavior
- Dates for standard tasks with durations longer than zero days recalculate correctly, but zero-day tasks remain stuck on their original dates.
Ensure you have administrative or editing privileges for the project schedule and verify that your calculation options are set to 'Automatic' before modifying calendar settings.
Adjust Task Calendar and Force Recalculation
Check the specific task constraints and manually force the software to recalculate the project schedule.
Zero-day tasks are typically treated as milestones. Sometimes, they hold onto specific calendar exceptions or lack the dependencies required to automatically shift when the global calendar changes.
Double-click the affected zero-day task to open the Task Information dialog box.
Navigate to the 'Advanced' tab. Under the Calendar dropdown, ensure it is set to 'None' (so it inherits the project calendar) or explicitly matches the newly updated project calendar.
Go to the 'Advanced' tab and check the 'Constraint type'. Ensure it is set to 'As Soon As Possible' rather than a hard constraint like 'Must Start On'.
Click 'OK' to save changes. Then, press F9 on your keyboard or go to the Project tab and click 'Calculate Project' to force a full schedule recalculation.

Manage Your Projects Easily with WPS Office
While specialized project software can be complex and expensive, WPS Office provides intuitive spreadsheet tools and free Gantt chart templates to manage project timelines without the steep learning curve.
- 1. Download WPS Office: Install WPS Office for free on your preferred device.
- 2. Open Template Library: Launch WPS Spreadsheet and search for 'Project' or 'Gantt' in the template homepage.
- 3. Customize Your Schedule: Select a template and start entering your project tasks, durations, and milestones immediately.

Frequently Asked Questions
Why are zero-day tasks treated differently in project software?
Zero-day tasks are typically identified as milestones. They represent a fixed point in time rather than an ongoing effort, which can sometimes cause scheduling algorithms to lock their dates unless they are explicitly linked to other tasks.
How do I force all project dates to recalculate?
You can manually force a recalculation of your entire project by pressing the F9 key on your keyboard, or by navigating to the Project tab and clicking the 'Calculate Project' button.
Can I create milestones without setting the task duration to zero?
Yes, you can mark any task as a milestone regardless of its duration. Double-click the task to open Task Information, go to the Advanced tab, and check the 'Mark task as milestone' option.