Delete a Task and Remove Circular References in Microsoft Project

Camila MilosovichCamila Milosovich Nov 14, 2026 868 views

Question details

The user needs to delete a task and resolve circular references or remaining subproject dependencies in Microsoft Project.

Delete a Task and Remove Circular References in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
A task reappears after deletion, or dependencies remain after a linked subproject is deleted.
Observed behavior
Task links, including summary-task or subproject relationships, may remain and interfere with deleting the task.
Before you start

Open the affected project in a task view and identify the task or deleted subproject involved. Note any predecessor and successor relationships that need to remain in the schedule.

Solution 1Recommended

Review task links and remove circular references

Use this method when a task reappears after deletion or a dependency loop may involve summary tasks.

1
Turn off automatic calculation

Go to File > Options > Schedule and turn off the option to calculate the project after each edit under Calculation.

2
Show all subtasks

In a task view, select View > Outline > All Subtasks so that you can inspect links across the project.

3
Display dependency columns

Use Add New Column in the task table to add Predecessors and Successors side by side.

4
Inspect and remove problem links

Review the Predecessors and Successors entries for the affected tasks and summary tasks. Remove links that create a circular chain or are no longer needed, while keeping valid dependencies.

5
Delete the task and recalculate

Select the task row and delete it, then return to File > Options > Schedule to restore the calculation setting. Save the project and check whether the task remains deleted.

Review task links and remove circular references
Review summary links carefully: Removing a dependency can change the schedule. Inspect both ends of each link before removing it.
Free Microsoft Office alternative

Use WPS Office for Project Documents and Spreadsheets

WPS Office is a free, lightweight alternative for everyday documents, spreadsheets, and presentations. Its familiar interface and Microsoft Office format compatibility make it easy to move existing work. It does not repair Microsoft Project task dependencies.

Track project task lists and related data in WPS SpreadsheetsWork with Microsoft Office formats including DOCX, XLSX, and PPTXUse a familiar interface for everyday office workMove existing documents and spreadsheets into a lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Where can I see both predecessors and successors in Microsoft Project?

In a task view, use Add New Column to insert the Predecessors and Successors columns side by side.

How do I show tasks hidden under summary tasks?

Select View > Outline > All Subtasks to expand the project outline before reviewing dependencies.

Should I remove every link from a summary task?

No. Review the summary task's Predecessors and Successors entries and remove links that create a circular reference or are no longer needed. Removing valid links can change the schedule.

What if links from a deleted subproject cannot be removed?

Inspect the remaining Predecessors and Successors entries on affected tasks. If you cannot remove the obsolete relationships, contact Microsoft Project support with the project file.

Can WPS Office fix circular references in Microsoft Project?

No. Resolve Microsoft Project dependencies in Project or with Microsoft support. WPS Spreadsheets can be used separately for project task lists in spreadsheet formats such as XLSX.