Delete a Microsoft Project Summary Task Without Deleting Subtasks

Chanuka GeekiyanageChanuka Geekiyanage Nov 13, 2026 868 views

Question details

The user needs to delete a summary task in Microsoft Project but keep all subtasks in the project schedule.

Delete a Microsoft Project Summary Task Without Deleting Subtasks
Product
Microsoft Project
Device & OS
not provided
Scenario
The user is reorganizing an existing Microsoft Project plan and wants to remove a parent task without losing its child tasks.
Observed behavior
Microsoft Project warns that deleting the summary task will also delete its subtasks, so the user needs a safe sequence to preserve them.
Before you start

Open the project in Microsoft Project and switch to the Gantt Chart or Task Sheet view so you can see task outline levels and the Task tab commands.

Solution 1Recommended

Outdent Subtasks and Delete the Summary Task

Use this method when you want to remove a parent task while keeping every subtask in the schedule.

In Microsoft Project, deleting a summary task normally removes the subtasks indented below it. Outdenting the subtasks first changes their outline level so they no longer belong to the summary task and are not selected for deletion.

1
Select every subtask under the parent task

In the Gantt Chart or Task Sheet view, click the first subtask row directly beneath the summary task, hold Shift, and click the last subtask row to select the full block of child tasks.

2
Outdent the selected subtasks

Go to the Task tab and click Outdent Task in the Schedule group. This moves the selected subtasks one level to the left, making them independent of the summary task.

3
Delete the former summary task

Click the row selector at the left edge of the summary task row to select the entire row, then press Delete or right-click the row selector and choose Delete Task. Project removes only the summary task.

4
Check scheduling warnings

Review the Indicators column or Task Inspector for changed predecessor and successor relationships, then update any task links or constraints affected by the new outline structure.

Outdent Subtasks and Delete the Summary Task
Subtask preservation completed: The former summary task is deleted, and the subtasks remain in the project as higher-level tasks.
Free Microsoft Office alternative

Use WPS Office Free for the Documents Around Your Microsoft Project Plan

WPS Office is a free, lightweight Office suite with a familiar ribbon interface. It opens, edits, and saves Microsoft Word, Excel, and PowerPoint files, making it easy to handle project documentation, trackers, and presentations alongside Microsoft Project.

  1. 1. Install WPS Office: Download WPS Office Free from the official WPS website and run the installer on your Windows or Mac computer.
  2. 2. Open or create project documentation: Launch WPS Writer, WPS Spreadsheets, or WPS Presentation to create or edit the documents, reports, and slide decks that support your project plan.
  3. 3. Save in Microsoft Office format: Click Menu > Save As and choose the corresponding Microsoft Word, Excel, or PowerPoint format so the files remain compatible with Microsoft Office users.
Keep project reporting, budget trackers, and stakeholder presentations in familiar Word, Excel, and PowerPoint formats.Free and lightweight Office suite that does not require a Microsoft 365 subscription.Familiar ribbon-style interface makes migration from Microsoft Office simple.Work with Microsoft Office formats while you keep the Microsoft Project .mpp schedule in Microsoft Project.
microsoft office alternative - wps office

Frequently Asked Questions

Does deleting a summary task in Microsoft Project always delete its subtasks?

Yes, if the subtasks are still indented under the summary task. Microsoft Project prompts that the child tasks will be deleted unless you outdent them first.

How do I outdent multiple subtasks at once?

Select the subtask rows directly under the parent, go to the Task tab, and click Outdent Task. All selected tasks move one outline level higher.

Why does Microsoft Project show warnings after I outdent tasks?

Outline changes can affect predecessor and successor links at summary level. Review the Indicators column or Task Inspector and update any links or constraints that changed.

Can WPS Office open Microsoft Project .mpp files?

No, WPS Office does not open .mpp files. Use Microsoft Project for scheduling; use WPS Office as a free alternative for related Word, Excel, and PowerPoint files.

What if pressing Delete only clears the task name?

Click the row selector cell on the far left of the task row to select the whole row, then press Delete or right-click the row selector and choose Delete Task.