Fix a $0.00 Baseline Cost in Microsoft Project
Question details
The user wants to understand why a Microsoft Project baseline cost is $0.00 and how to record the planned project cost.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A project baseline has been saved, and the user wants to compare its cost with the total project cost.
- Observed behavior
- The baseline cost displays $0.00, potentially because costs, rates, or resource assignments were not in place when the baseline was saved.
Open the project in Microsoft Project and check whether a baseline has already been saved. Decide whether you need to preserve the existing baseline before replacing it.
Configure Project Costs and Save the Baseline
Use this method when costs were missing or incomplete when the project baseline was saved.
A baseline captures planned values at the time it is saved. Adding costs afterward does not automatically update the baseline cost.
Open View > Gantt Chart to review the task list, then open View > Resource Sheet to add the resources needed for the project.
In View > Resource Sheet, enter applicable values in the Std. Rate column for work resources. Set other relevant resource costs as needed.
In View > Gantt Chart, select a task and choose Resource > Assign Resources. Select the appropriate resources and click Assign.
In the Gantt Chart, choose View > Tables > Cost. Check the total costs and enter any applicable fixed costs before saving the baseline.
Choose Project > Set Baseline > Set Baseline, select a baseline and Entire project, then click OK. If prompted to overwrite an existing baseline, confirm only if you intend to replace it.
In View > Tables > Cost, compare the Baseline and Total Cost columns. To see the project-level total, enable Format > Project Summary Task in the Gantt Chart.

Review Project Cost Spreadsheets with WPS Office
WPS Office is a free, lightweight alternative for working with office documents in a familiar interface. Use WPS Spreadsheets to review project cost data in Excel format, making it easy to move spreadsheet work from Microsoft Office. It does not fix Microsoft Project baselines.

Frequently Asked Questions
Why is my baseline cost still zero after I added resource rates?
The baseline records costs as they stood when it was saved. After entering rates and assigning resources, review View > Tables > Cost, then save or update a baseline through Project > Set Baseline.
Will the baseline cost equal the total project cost?
For an entire-project baseline, the baseline cost should reflect the project's scheduled total cost when the baseline is saved. The current total cost can differ later if costs or assignments change.
Where can I see the baseline cost for the whole project?
In Gantt Chart view, enable Format > Project Summary Task, then choose View > Tables > Cost. Check the Baseline and Total Cost values on the project summary row.
Can I save a new baseline without replacing the original?
Yes. Choose Project > Set Baseline > Set Baseline and select an unused baseline, such as Baseline1. This keeps the original baseline available for comparison.