Fix a $0.00 Baseline Cost in Microsoft Project

Elise WilliamsElise Williams Nov 20, 2026 868 views

Question details

The user wants to understand why a Microsoft Project baseline cost is $0.00 and how to record the planned project cost.

Why Does Microsoft Project Show a $0.00 Baseline Cost?
Product
Microsoft Project
Device & OS
not provided
Scenario
A project baseline has been saved, and the user wants to compare its cost with the total project cost.
Observed behavior
The baseline cost displays $0.00, potentially because costs, rates, or resource assignments were not in place when the baseline was saved.
Before you start

Open the project in Microsoft Project and check whether a baseline has already been saved. Decide whether you need to preserve the existing baseline before replacing it.

Solution 1Recommended

Configure Project Costs and Save the Baseline

Use this method when costs were missing or incomplete when the project baseline was saved.

A baseline captures planned values at the time it is saved. Adding costs afterward does not automatically update the baseline cost.

1
Check tasks and resources

Open View > Gantt Chart to review the task list, then open View > Resource Sheet to add the resources needed for the project.

2
Enter resource rates

In View > Resource Sheet, enter applicable values in the Std. Rate column for work resources. Set other relevant resource costs as needed.

3
Assign resources to tasks

In View > Gantt Chart, select a task and choose Resource > Assign Resources. Select the appropriate resources and click Assign.

4
Review calculated costs

In the Gantt Chart, choose View > Tables > Cost. Check the total costs and enter any applicable fixed costs before saving the baseline.

5
Save the baseline

Choose Project > Set Baseline > Set Baseline, select a baseline and Entire project, then click OK. If prompted to overwrite an existing baseline, confirm only if you intend to replace it.

6
Compare project costs

In View > Tables > Cost, compare the Baseline and Total Cost columns. To see the project-level total, enable Format > Project Summary Task in the Gantt Chart.

Configure Project Costs and Save the Baseline
Preserve an existing baseline: If you need the original baseline for comparison, select an unused baseline such as Baseline1 instead of overwriting it.
Free Microsoft Office alternative

Review Project Cost Spreadsheets with WPS Office

WPS Office is a free, lightweight alternative for working with office documents in a familiar interface. Use WPS Spreadsheets to review project cost data in Excel format, making it easy to move spreadsheet work from Microsoft Office. It does not fix Microsoft Project baselines.

Review project cost data in spreadsheet tablesOpen and edit Microsoft Excel XLSX filesWork with a familiar spreadsheet interfaceUse a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why is my baseline cost still zero after I added resource rates?

The baseline records costs as they stood when it was saved. After entering rates and assigning resources, review View > Tables > Cost, then save or update a baseline through Project > Set Baseline.

Will the baseline cost equal the total project cost?

For an entire-project baseline, the baseline cost should reflect the project's scheduled total cost when the baseline is saved. The current total cost can differ later if costs or assignments change.

Where can I see the baseline cost for the whole project?

In Gantt Chart view, enable Format > Project Summary Task, then choose View > Tables > Cost. Check the Baseline and Total Cost values on the project summary row.

Can I save a new baseline without replacing the original?

Yes. Choose Project > Set Baseline > Set Baseline and select an unused baseline, such as Baseline1. This keeps the original baseline available for comparison.