Fix Missing Timeline Tasks in Microsoft Project Master Projects
Question details
The user needs tasks and milestones from multiple subprojects to appear correctly on a Microsoft Project master timeline.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A master project combines multiple subprojects and displays selected tasks and milestones on its timeline.
- Observed behavior
- Timeline items from one subproject appear to replace, hide, or incorrectly mark items from another subproject.
Identify the affected subprojects and note which tasks or milestones are missing from the master timeline. Check the Project version and update status on each installation used to edit the files.
Update Microsoft Project and check the affected subprojects
Start here to rule out an outdated installation or a compatibility issue before rebuilding the timeline.
In Microsoft Project, open File > Account > Update Options > Update Now if that option is available. If updates are managed by your organization, ask your administrator to check them.
Open File > Account > About Project and compare the version with the installations used to edit the subprojects. Make sure the files can be opened and edited in compatible, supported versions.
Open each affected subproject separately and check the tasks and milestones that are missing from the master timeline. Note whether the affected projects were copied from the same file or template, which may help narrow down the conflict.
Reopen the master project and check its Timeline view. If an item is absent, right-click the task or milestone in the task list and select Add to Timeline, then check whether items from other subprojects remain visible.

Create a static master project and rebuild the timeline
Use a static master as a workaround if the linked master timeline remains unreliable after updating Project.
Use WPS Spreadsheets for Project Status Reporting
WPS Office is a free, lightweight alternative for everyday office work. Export project information to an Excel workbook, then use the familiar WPS Spreadsheets interface to review and share task status. WPS does not repair Microsoft Project timelines.

Frequently Asked Questions
How do I add a missing milestone back to the timeline?
In the master project's task list, right-click the milestone and select Add to Timeline. Check whether adding it causes another subproject's timeline item to disappear.
Can copied project templates cause timeline conflicts?
Copied files or templates and duplicate identifiers are possible clues, but they do not prove the cause. Open the affected subprojects separately and compare them with an independently created project.
Will a static master update when a subproject changes?
No. If you insert a subproject with Link to project cleared, the static master contains a copy. Rebuild or update that copy when the original subproject changes.
Can WPS Office fix the Microsoft Project timeline?
No. Update and troubleshoot the timeline in Microsoft Project. For separate status reporting, export project information to an Excel workbook and open it in WPS Spreadsheets.