Fix Project Online Resource Engagements Missing from Resource Requests
Question details
Users notice that active resource engagements are unexpectedly missing or disappearing from the Resource Requests page.

- Product
- Project Online
- Device & OS
- not provided
- Scenario
- Viewing active committed engagements on the Resource Requests page after some time has passed.
- Observed behavior
- Engagements disappear from the Resource Requests view when the proposed engagement end date is more than three months in the past, even if the committed engagement is still active.
Ensure you have the necessary resource manager permissions in Project Online and check if any custom filters are applied to your current Resource Requests view.
Extend the Proposed Engagement Dates
Prevent engagements from being filtered out by manually keeping the proposed engagement dates aligned with the committed engagement dates.
Project Online applies a built-in filter to improve performance on the Resource Requests page. If the proposed end date is more than three months in the past, the engagement will be hidden from this specific view, even if the actual commitment was manually extended.
Navigate to the Resource Requests page in your Project Online environment.
Find the specific resource engagement before the proposed end date becomes older than three months.
Manually edit the proposed engagement end date so that it matches or exceeds the newly extended committed engagement date.
Save your modifications. The engagement will now remain visible in the standard Resource Requests view.

View Engagements via Power BI or Resource Plan View
Bypass the three-month filter entirely by using alternative reporting and viewing tools that do not apply this restriction.
Manage Project Data Easily with WPS Office
If complex enterprise tools like Project Online are causing friction with hidden data and rigid filters, consider managing simpler project timelines and resource allocations using WPS Spreadsheet. WPS Office is a free, lightweight suite fully compatible with Microsoft Office formats.
- 1. Download WPS Office: Visit the official WPS website and download the free WPS Office suite.
- 2. Open WPS Spreadsheet: Launch WPS Spreadsheet to start organizing your resource data.
- 3. Use a Project Template: Access the built-in template library to find ready-to-use resource management and project tracking templates.

Frequently Asked Questions
Why do my active resource engagements suddenly disappear in Project Online?
Project Online automatically hides engagements from the Resource Requests page if the initial proposed engagement end date is more than three months in the past. This happens even if you have manually extended the actual commitment.
Can I disable the three-month filter on the Resource Requests page?
No, this is a built-in performance optimization feature in Project Online. You must either update the proposed engagement dates to keep them current or use a different reporting view like Power BI.
Will I lose the data for engagements that disappear from the view?
No, the data is not deleted. The engagement is simply filtered out of the online Resource Requests page. You can still access and view it using Power BI or the desktop application's Resource Plan view.