Fix Project Online Tasks Not Appearing in Quick Launch

Phi Hung VoPhi Hung Vo Nov 2, 2026 869 views

Question details

Assigned tasks in Project Online fail to display in the Tasks Quick Launch or Project Site task list, despite assignments being visible in the Resource Center.

Fix Project Online Tasks Not Appearing for Resources in Quick Launch
Product
Microsoft Project Online
Device & OS
not provided
Scenario
Resources check their Tasks Quick Launch to view and update their assigned project tasks.
Observed behavior
Tasks do not appear in the Quick Launch or Project Site task list for the resources, even after the tasks are published and resources are properly assigned.
Before you start

Ensure you have the necessary project manager permissions to open and check out the enterprise project in the Microsoft Project desktop client before making resource booking changes.

Solution 1Recommended

Change Resource Booking from Proposed to Committed

Tasks will not appear in the Quick Launch for resources whose booking status is set to 'Proposed'. Updating the status to 'Committed' resolves this visibility issue.

When managing enterprise resources in Project Online, the Booking status determines how assignments are treated. 'Proposed' resources are typically used for tentative planning and capacity analysis, meaning their specific task assignments won't reflect in their operational Quick Launch. You must commit these resources to make the tasks actionable.

1
Open the project

Launch Microsoft Project desktop client, connect to Project Web App (PWA), and check out the specific project you need to modify.

2
Access the Build Team dialog

Navigate to the 'Resource' tab on the ribbon and click on 'Build Team from Enterprise'.

3
Review and change booking values

In the right pane showing the project resources, locate the 'Booking' column. For every enterprise resource assigned to the missing tasks, change the dropdown value from 'Proposed' to 'Committed'.

4
Save and republish

Click 'OK' to close the dialog. Save the project locally, then go to 'File' > 'Publish' to republish the latest changes to Project Online.

Change Resource Booking from Proposed to Committed
Additional Checks: If all resources are already marked as 'Committed' and the issue persists, contact your Project Online administrator to verify assignment ownership, check for stuck publishing jobs in the PWA queue, and confirm site synchronization settings.
Free Microsoft Office alternative

Manage Project Plans and Tasks with WPS Office

If you are looking for a simpler way to track team tasks without the complexity of enterprise project management systems, WPS Office offers a free, lightweight, and highly compatible alternative. You can easily manage timelines, collaborate on task lists, and share reports.

  1. 1. Download and Install: Download WPS Office for free from the official website and install it on your device.
  2. 2. Choose a Template: Open WPS Spreadsheet, go to the Template Library, and search for 'Project Task Tracker' or 'Gantt Chart'.
  3. 3. Customize and Share: Fill in your project tasks, assign them to team members, and save the file in .xlsx format to share with your team seamlessly.
Highly compatible with Microsoft Excel (.xlsx), Word (.docx), and PowerPoint (.pptx) formats.Rich library of free Gantt chart and task tracker templates to organize project tasks quickly.Lightweight installation with a familiar, easy-to-use tabbed interface for seamless migration.Built-in PDF tools for generating and sharing professional project status reports.
microsoft office alternative - wps office

Frequently Asked Questions

Why are published tasks not showing up in Project Online?

This usually happens because the assigned resources are set to 'Proposed' rather than 'Committed' in the Build Team dialog. It can also occur if the project publication failed or if project site synchronization is disabled.

How do I check if a resource is Committed in Microsoft Project?

Open your project in the Microsoft Project Desktop client, navigate to the Resource tab, and click 'Build Team from Enterprise'. Check the 'Booking' column next to the resource names to see if they are Proposed or Committed.

What should I do if resources are already committed but tasks are still missing?

You should check the Manage Queue page in PWA to ensure the publish job completed successfully. Additionally, verify that the 'Assignment Owner' is set correctly for the resource, and ask your administrator to check the User Profile Sync and Project Site sync settings.