How to Copy Tasks in Microsoft Project Without Breaking Predecessors

Steve KSteve K Nov 3, 2026 868 views

Question details

The user needs to copy a group of tasks in Microsoft Project without the predecessor links remaining tied to the original source tasks.

How to Copy Tasks in Microsoft Project Without Breaking Predecessors
Product
Microsoft Project
Device & OS
not provided
Scenario
Copying and pasting task groups or multiple projects within a Microsoft Project schedule.
Observed behavior
Predecessor links remain tied to the original task IDs instead of automatically updating to reference the newly pasted copied tasks.
Before you start

Take note of the starting and ending task IDs of the group you intend to copy so you can quickly verify that the predecessor links have updated successfully after pasting.

Solution 1Recommended

Select Entire Task Rows Before Copying

Selecting the complete task rows forces Microsoft Project to capture and update the internal task relationships upon pasting.

The most common reason predecessor links fail to update is that users only highlight the visible cells (e.g., from Task Name to Predecessors). Microsoft Project treats cell-only selections as literal text values. By selecting the entire row, Project recognizes the tasks as logical objects and automatically calculates the offset for task dependencies when pasted.

1
Select the rows

Click on the row header (the gray numbered cell on the far left) for the first task you want to copy, hold the Shift key, and click the row header for the last task to select entire rows.

2
Copy the selection

Press Ctrl+C on your keyboard, or right-click the row headers and choose 'Copy' from the context menu.

3
Paste into the destination

Click the row header of the destination row below your original group and press Ctrl+V to paste the tasks.

4
Verify predecessor links

Check the 'Predecessors' column in the newly pasted tasks to ensure the dependency IDs have updated to reference the new block of tasks rather than the original lines.

Select Entire Task Rows Before Copying
Verification Tip: By copying the entire row, Microsoft Project automatically calculates the offset and updates the predecessor task IDs to match the new pasted block perfectly.
Free Microsoft Office alternative

Need a Lightweight, Affordable Office Suite? Try WPS Office

While Microsoft Project handles complex project scheduling, you might also need a reliable, affordable solution for your daily documents, spreadsheets, and presentations. WPS Office is a highly compatible, free alternative to Microsoft Office that covers all your core productivity needs.

  1. 1. Download and Install: Download WPS Office for free from the official website and follow the quick installation process.
  2. 2. Open Your Files: Launch WPS Office and open your existing .docx, .xlsx, or .pptx files natively without worrying about formatting issues.
  3. 3. Start Working: Enjoy the seamless editing experience with a familiar tabbed interface that boosts your productivity.
Fully compatible with Microsoft Word, Excel, and PowerPoint file formats.Lightweight installation that runs incredibly smoothly on older devices.Familiar ribbon interface ensures zero learning curve when transitioning from MS Office.Built-in PDF editor to easily manage, convert, and share project reports.
microsoft office alternative - wps office

Frequently Asked Questions

Why do my predecessors link back to the original task in MS Project?

This happens when you only copy individual data cells rather than full task rows. Because the full row wasn't selected, Microsoft Project treats the action as copying literal text values, keeping the old task IDs completely intact.

Can I copy a task without copying its predecessor links?

Yes. To copy a task without bringing over its predecessor dependencies, you can copy just the 'Task Name' cell and paste it into a new row. The new task will be created cleanly without any linked predecessors.

Does copying whole rows work for copying tasks between different Project files?

Copying entire rows generally works between different Microsoft Project files. However, depending on your global settings and resource pools, cross-project links might prompt you to create external links instead of simple internal predecessors.