How to Display a Custom Microsoft Project Duration Column in Hours
Question details
The user needs to display project task durations strictly in hours using a custom column, avoiding the default duration unit settings.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Creating a custom column in a project schedule to independently display task durations in hours without affecting or inheriting the standard project-wide duration units.
- Observed behavior
- Microsoft Project normally forces custom duration fields to inherit the standard Duration unit (such as days), which prevents custom columns from displaying hours separately.
Ensure you have your Microsoft Project schedule open and that you have the necessary permissions to add custom fields and define custom formulas within the project file.
Use the ProjDurConv Formula in a Custom Number Field
Convert standard duration values accurately into hours using the native project duration conversion formula.
This method converts the underlying duration data directly into hours without appending text. It is ideal when you need to use the resulting numerical data for further calculations.
Right-click the column header area in your Gantt Chart view, select 'Custom Fields', and choose 'Number' from the Type dropdown menu at the top right.
Select an available number field (e.g., Number1), click the 'Formula...' button under Custom attributes, and input ProjDurConv([Duration], pjHours) in the formula box. Click OK.
To ensure summary tasks also display the calculated hours, go to the 'Calculation for task and group summary rows' section in the Custom Fields dialog and select the 'Use formula' option.

Create a Custom Text Field for Formatted Display
Use this method if you want the custom column to explicitly display the text 'hours' next to the numeric value.
Manage Project Schedules and Trackers with WPS Office
While Microsoft Project handles specialized complex scheduling, you can easily manage project timelines, trackers, and task lists using WPS Spreadsheet. It serves as a highly compatible, free, and lightweight alternative to Microsoft Office for everyday project management.
- 1. Download and Install WPS Office: Visit the official WPS Office website to download the free suite and install it on your device.
- 2. Open WPS Spreadsheet: Launch WPS Office and click on 'Spreadsheet' to start a new workbook or open an existing project tracker.
- 3. Use Project Management Templates: Browse the built-in template library to find ready-to-use Gantt charts, task lists, and project timeline templates to easily manage your workflow.

Frequently Asked Questions
Why does my custom duration field still show in days?
By default, custom duration fields in Microsoft Project inherit the standard Duration unit setting (often days). To display hours independently, you must bypass this by using specific calculation formulas like ProjDurConv in a Number field or formatting a Text field.
How do I include summary tasks in my custom duration formula?
When setting up your custom field formula in the Custom Fields dialog box, ensure you check the option for 'Use formula' located under the 'Calculation for task and group summary rows' section.
Can I change the default duration unit for the entire project instead of creating a custom column?
Yes, you can change the default duration unit for the whole project by navigating to File > Options > Schedule, and changing 'Duration is entered in' to Hours. Note that this will affect all standard duration fields across the entire project schedule.