How to Display Milestones from Microsoft Project Subplans in a Master Plan
Question details
The user needs to know how to keep milestones from linked Microsoft Project subprojects continuously visible, as they currently disappear when the master plan is reopened.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Managing a dynamic master plan with linked subprojects to track project milestones.
- Observed behavior
- Milestones from linked subprojects only appear after manually expanding and collapsing each subproject row, and this display state is not retained upon reopening the master file.
Ensure that your master plan and all linked subproject files are saved in their correct directory locations to prevent broken pointers or missing data.
Expand Subprojects and Save the Master Plan
Refresh the dynamic pointers in your master plan by expanding the subprojects, which fetches the latest rolled-up milestones from the linked files.
In Microsoft Project, a dynamic master plan does not store the actual data of the subprojects; it merely holds pointers to those files, while the summary rows belong directly to the master plan. Because of this structure, the master file may not immediately retrieve subproject milestones upon opening. This behavior is expected and does not indicate a bug or a corrupted software installation.
Launch Microsoft Project and open your dynamic master plan containing the linked subprojects.
Click the expand icon (the plus sign) next to each linked subproject. This action forces the master file to query the subprojects and display the updated rolled-up milestones.
Once the milestones are refreshed and displayed, you can click the collapse icon (the minus sign) if you prefer to view only the summary.
Click on 'File' and select 'Save'. If prompted by Microsoft Project to save changes to the linked subprojects as well, accept the prompt to ensure the refreshed states are properly recorded.

Plan and Track Project Milestones Efficiently with WPS Office
While WPS Office does not natively support Microsoft Project (.mpp) files, WPS Spreadsheet is an excellent, free alternative for organizing project schedules, managing milestones, and building Gantt charts without dealing with complex dynamic linking issues.
- 1. Download and launch WPS Office: Install WPS Office for free and open the WPS Spreadsheet module.
- 2. Find a project template: Navigate to the 'Templates' section and search for 'Project Plan' or 'Gantt Chart' to find a pre-built project tracking sheet.
- 3. Input milestones and save: Customize the template with your specific project milestones, update timelines, and save your document in standard .xlsx format to share with stakeholders.

Frequently Asked Questions
Why do my subproject milestones disappear when reopening the master plan?
Dynamic master plans store pointers rather than the actual subproject data. When you reopen the file, Microsoft Project requires you to expand the subproject sections to refresh the connection and fetch the updated milestones.
Is my Microsoft Project file corrupted if the summary rows are empty?
No. This is expected behavior for linked files in a dynamic master plan. The data is safe within the subproject files and simply needs to be visually refreshed by expanding the subproject rows.
Should I reinstall Microsoft Project to fix this milestone visibility issue?
No, reinstalling Microsoft Project will not alter this behavior. It is a fundamental design of how dynamic master plans handle rolled-up data. Manually expanding and saving the subprojects is the correct resolution.




