How to Manage More Than 50 Similar Projects in Microsoft Project

Tauseeq MagsiTauseeq Magsi Nov 13, 2026 869 views

Question details

A telecommunications organization needs a repeatable way to plan, track, and report on more than 50 cell tower construction projects that follow the same workflow in Microsoft Project.

How to Manage More Than 50 Similar Projects in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Portfolio management of 50+ similar cell tower construction schedules with shared tasks, phases, and milestones.
Observed behavior
The organization needs to plan and track the projects consistently, capture actual dates and completion percentages, and create portfolio-level reports.
Before you start

Confirm that all 50+ cell tower projects share the same task sequence, phases, milestones, and reporting fields, and make sure each project file uses the same version of Microsoft Project before creating a template or master project.

Solution 1Recommended

Create a Microsoft Project template and set a baseline for every tower project

Use this when the 50+ projects share the same tasks, dependencies, durations, phases, and milestones, so each new tower schedule starts from one standard plan.

A shared template prevents inconsistent schedules and makes it easier to compare status, track actuals, and report progress across the entire portfolio.

1
Build the standard project schedule

Open Microsoft Project, create a new blank project, and enter the standard tasks, phases, milestones, durations, task dependencies, and resource names that all cell tower construction projects share.

2
Save the file as a Project template

Go to File > Save As, choose Project Template (.mpt) as the file type, and save it with a clear name such as 'Cell Tower Construction Template'.

3
Create each tower project from the template

For each new tower, click File > New > Personal or choose the saved template, enter the tower name, and set the project start date.

4
Save a baseline for each project

With the new project open, click Project > Set Baseline > Set Baseline, choose Entire project, and select OK before entering actual progress.

5
Record actual dates and completion percentages

Update the task sheet with actual start/finish dates, remaining duration, and percent complete, then reschedule remaining work as needed.

Create a Microsoft Project template and set a baseline for every tower project
Portfolio-ready schedules: Every tower schedule stays comparable because each project starts from the same template and has a saved baseline for variance analysis.
Free Microsoft Office alternative

Use WPS Office for Lightweight Project Reporting and Office File Editing

WPS Office does not include Microsoft Project, but it is a free, lightweight Office alternative that opens Excel, Word, and PowerPoint files with high compatibility. Project teams can track exported project data, milestones, and reports in WPS Spreadsheet without an expensive Microsoft Office license.

Free, lightweight Office suite for tracking exported project data in WPS SpreadsheetHigh compatibility with .xlsx, .docx, and .pptx Microsoft Office formatsFamiliar ribbon UI helps project teams move from Microsoft Office quicklyUse WPS Spreadsheet to consolidate exported milestones, baselines, and completion reports
microsoft office alternative - wps office

Frequently Asked Questions

Can I manage more than 50 similar projects without creating a separate schedule from scratch?

Yes. Create one Microsoft Project template with the standard tasks, dependencies, phases, milestones, and durations, then start every new tower project from that template and save a baseline.

How do I create a master project in Microsoft Project?

Open a new blank project, go to the Project tab, select Subproject > Insert Subproject, and choose the individual tower project files. The master project lets you view and report on all inserted schedules together.

Will WPS Office open Microsoft Project .mpp files?

No, WPS Office does not open .mpp files. Use Microsoft Project for scheduling, export project data to Excel, and open the exported workbook in WPS Spreadsheet for further reporting and sharing.

What is the benefit of saving a baseline in Microsoft Project?

A baseline captures the original planned dates, work, and cost before progress is recorded, so you can compare planned values against actual dates and completion percentages later.

Can WPS Office be used to track project milestones?

Yes. You can use WPS Spreadsheet to create a milestone tracker with columns for project name, planned date, actual date, and status, and use conditional formatting or charts to monitor the portfolio.