How to Manage More Than 50 Similar Projects in Microsoft Project
Question details
A telecommunications organization needs a repeatable way to plan, track, and report on more than 50 cell tower construction projects that follow the same workflow in Microsoft Project.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Portfolio management of 50+ similar cell tower construction schedules with shared tasks, phases, and milestones.
- Observed behavior
- The organization needs to plan and track the projects consistently, capture actual dates and completion percentages, and create portfolio-level reports.
Confirm that all 50+ cell tower projects share the same task sequence, phases, milestones, and reporting fields, and make sure each project file uses the same version of Microsoft Project before creating a template or master project.
Create a Microsoft Project template and set a baseline for every tower project
Use this when the 50+ projects share the same tasks, dependencies, durations, phases, and milestones, so each new tower schedule starts from one standard plan.
A shared template prevents inconsistent schedules and makes it easier to compare status, track actuals, and report progress across the entire portfolio.
Open Microsoft Project, create a new blank project, and enter the standard tasks, phases, milestones, durations, task dependencies, and resource names that all cell tower construction projects share.
Go to File > Save As, choose Project Template (.mpt) as the file type, and save it with a clear name such as 'Cell Tower Construction Template'.
For each new tower, click File > New > Personal or choose the saved template, enter the tower name, and set the project start date.
With the new project open, click Project > Set Baseline > Set Baseline, choose Entire project, and select OK before entering actual progress.
Update the task sheet with actual start/finish dates, remaining duration, and percent complete, then reschedule remaining work as needed.

Consolidate all schedules into a master project for portfolio-level reporting
Use this when you need a single Microsoft Project file that shows all 50+ tower projects for executive reports, resource reviews, and critical path analysis.
Use WPS Office for Lightweight Project Reporting and Office File Editing
WPS Office does not include Microsoft Project, but it is a free, lightweight Office alternative that opens Excel, Word, and PowerPoint files with high compatibility. Project teams can track exported project data, milestones, and reports in WPS Spreadsheet without an expensive Microsoft Office license.

Frequently Asked Questions
Can I manage more than 50 similar projects without creating a separate schedule from scratch?
Yes. Create one Microsoft Project template with the standard tasks, dependencies, phases, milestones, and durations, then start every new tower project from that template and save a baseline.
How do I create a master project in Microsoft Project?
Open a new blank project, go to the Project tab, select Subproject > Insert Subproject, and choose the individual tower project files. The master project lets you view and report on all inserted schedules together.
Will WPS Office open Microsoft Project .mpp files?
No, WPS Office does not open .mpp files. Use Microsoft Project for scheduling, export project data to Excel, and open the exported workbook in WPS Spreadsheet for further reporting and sharing.
What is the benefit of saving a baseline in Microsoft Project?
A baseline captures the original planned dates, work, and cost before progress is recorded, so you can compare planned values against actual dates and completion percentages later.
Can WPS Office be used to track project milestones?
Yes. You can use WPS Spreadsheet to create a milestone tracker with columns for project name, planned date, actual date, and status, and use conditional formatting or charts to monitor the portfolio.