How to Prevent Duration Changes When Unlinking Microsoft Project Subprojects
Question details
Users need a way to unlink subprojects from a Microsoft Project master schedule without causing unintended task duration changes.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Managing a master schedule with multiple subprojects containing various working-time calendars and shifts.
- Observed behavior
- Task durations automatically change and recalculate when the dynamic links between the master project and subprojects are broken due to mismatched calendar settings.
Before breaking any dynamic links in your master project, ensure you have backed up all schedule files and documented the exact working-time calendars currently used across all subprojects.
Standardize Calendars and Adjust Duration Inputs
Aligning calendar settings across the master and subprojects prevents recalculations when unlinking.
When subprojects use different calendars (such as 8, 10, 12, or 24-hour shifts) compared to the master project, MS Project recalculates durations based on the master's default working day once links are broken. Standardizing these calendars prevents this mismatch.
Open the master project, navigate to the 'Project' tab on the ribbon, and select 'Change Working Time'.
Review the working day lengths, shift times, and exceptions, ensuring they perfectly align with the calendars set in your individual subprojects.
Go to File > Options > Schedule and ensure the 'Hours per day' value matches the standardized calendar structure.
Instead of defining durations in days, enter all task durations in hours (e.g., type '24h' instead of '3d') to force the software to respect absolute time rather than variable daily schedules.

Keep Subprojects Linked in a Stable Environment
If time constraints prevent you from standardizing complex calendars, maintaining the dynamic links in a highly controlled environment is the safest alternative.
Manage Your Project Documentation with WPS Office
While Microsoft Project handles complex master scheduling, WPS Office provides a free, lightweight, and highly compatible suite for managing all your project documentation, reports, and spreadsheets without the hassle of link corruption.
- 1. Download the installer: Visit the official WPS Office website and download the free installation package for your operating system.
- 2. Install the software: Run the downloaded installer and follow the quick on-screen instructions to set up WPS Office on your device.
- 3. Open project documents: Launch WPS Office and directly open any existing Microsoft Office files to start managing your project reports and data instantly.

Frequently Asked Questions
Why do task durations change when I unlink a subproject in Microsoft Project?
This occurs when the subproject and master project use different working-time calendars. Upon unlinking, the tasks revert to the master project's default calendar, causing MS Project to recalculate task durations based on different daily working hours.
Can I use SharePoint to host dynamically linked master and subprojects?
It is highly discouraged. Dynamically linked Project structures often become corrupted when stored on SharePoint or remote web servers. It is best to keep them in a single folder on a local drive or a stable shared network drive.
How can I accurately record task durations when dealing with multiple shift schedules?
When managing multiple shifts (such as 8, 10, 12, or 24-hour schedules), it is best to enter task durations in absolute hours (e.g., '40h') rather than days ('5d'). This prevents the software from recalculating durations based on a generic 8-hour workday assumption.