How to Remove Dates Displayed Next to Milestones in Microsoft Project

Bushra ParveenBushra Parveen Nov 2, 2026 869 views

Question details

The user needs to hide or remove the finish dates that automatically display next to milestone symbols in the Gantt Chart view.

How to Remove Dates Displayed Next to Milestones in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Formatting a project schedule and Gantt chart to create a cleaner visual presentation without cluttered date labels.
Observed behavior
Microsoft Project displays a milestone's finish date to the right of its diamond symbol by default in the Gantt Chart.
Before you start

Ensure you have your Microsoft Project file open and are currently viewing the Gantt Chart where the milestones are visible.

Solution 1Recommended

Modify Global Milestone Bar Styles

Use this method to change the default formatting for all milestones in your project so dates no longer appear automatically.

By default, Microsoft Project's global bar styles are configured to show the finish date to the right of milestone symbols. Modifying this global setting is the most efficient way to clean up your entire Gantt chart at once.

1
Open Bar Styles

Navigate to the Format tab on the ribbon and click on 'Bar Styles' to open the configuration window.

2
Select Milestone Style

In the Bar Styles dialog box, scroll through the list of task types and click on the 'Milestone' row to select it.

3
Edit Text Settings

Look at the lower section of the window and click on the 'Text' tab.

4
Remove the Date Field

Locate the 'Right' field, which currently displays 'Finish'. Delete this text, or select one of the blank text fields (like Text1-Text12) from the drop-down menu to clear it.

5
Apply Changes

Click 'OK' to save your changes. The dates should immediately disappear from the milestones on your Gantt chart.

Modify Global Milestone Bar Styles
Tip: If you want to display other information instead, you can choose different fields like 'Task Name' or 'Resource Names' from the drop-down menu.
Free Microsoft Office alternative

Need a Free Alternative for Managing Project Documents?

While Microsoft Project is designed for complex scheduling, WPS Office provides a free, lightweight suite for managing all your project documents, tracking spreadsheets, and presentations with seamless Microsoft Office compatibility.

  1. 1. Download and Install: Get WPS Office from the official website and install it on your device.
  2. 2. Open a Project Template: Launch WPS Spreadsheet and search for 'Project Management' or 'Gantt Chart' in the free template library.
  3. 3. Customize Your Tracker: Input your task names, start dates, and durations to instantly generate a clean project timeline.
Fully compatible with Microsoft Word, Excel, and PowerPoint file formats.Easily create comprehensive project tracking spreadsheets and simple Gantt charts in WPS Spreadsheet.Lightweight software that runs smoothly on Windows, Mac, Linux, and mobile devices.Free to use with a familiar, easy-to-navigate tabbed interface, making migration effortless.
microsoft office alternative - wps office

Frequently Asked Questions

Why do dates still appear next to my milestone after changing the Bar Styles?

This usually happens when the individual milestone has custom formatting applied that overrides the global setting. You must select the specific milestone, open the Format Bar window, and click 'Reset' to make it follow your updated global Bar Styles settings.

Can I display other information instead of the finish date next to a milestone?

Yes. In the Bar Styles text settings, you can click the drop-down for the 'Right', 'Left', 'Top', or 'Bottom' fields and choose different project data, such as task names, resource initials, or custom text fields.

How do I show dates only for specific milestones in Microsoft Project?

First, remove the dates from the global milestone style in 'Format > Bar Styles'. Then, double-click the individual milestones where you want dates to appear and manually add the 'Finish' field to the text settings in the 'Format Bar' window.