How to Remove Decimal Days from Microsoft Project Durations

Partner EditorPartner Editor Oct 1, 2026 868 views

Question details

The user wants to stop Microsoft Project from displaying fractional or decimal task durations and properly configure the schedule for projects measured in strict calendar days.

How to Remove Decimal Days from Microsoft Project Durations
Product
Microsoft Project
Device & OS
not provided
Scenario
Setting up project timelines and task dependencies where contract periods are measured in absolute calendar days rather than standard working hours.
Observed behavior
Task durations are displaying as decimal or fractional days (e.g., 3.25 days) instead of whole numbers.
Before you start

Before adjusting task durations, ensure that your project's default start times, working hours, and holiday exceptions are clearly defined so your calendar accurately reflects the real-world schedule.

Solution 1Recommended

Use Elapsed Durations for Calendar Days

If your project contract requires strictly calendar days without factoring in weekends or holidays, using the elapsed duration format is the quickest and most effective fix.

Elapsed durations calculate time based on a continuous 24-hour day and 7-day week, entirely ignoring the project's non-working time calendar. This is ideal for tasks like curing concrete or contract periods measured in true calendar days.

1
Select the task duration

In your Gantt Chart view, click on the Duration cell for the task you want to modify.

2
Enter the elapsed duration

Type your desired number of days immediately followed by 'ed' (for example, type '10ed' for 10 elapsed days).

3
Apply the change

Press Enter. Microsoft Project will now schedule this task using uninterrupted time, removing any unwanted decimal fractions caused by working-hour gaps.

Use Elapsed Durations for Calendar Days
Quick Tip: You can also use 'ew' for elapsed weeks or 'em' for elapsed months depending on your project scale.
Free Microsoft Office alternative

Manage Your Projects Easily with WPS Office

While Microsoft Project handles complex dependency scheduling, WPS Office provides a free, lightweight, and highly compatible alternative for general project tracking. Using WPS Spreadsheet, you can easily build Gantt charts, track task durations, and manage timelines without dealing with convoluted calendar settings or high software costs.

  1. 1. Download the software: Visit the official WPS Office website and download the free installation package for your operating system.
  2. 2. Install WPS Office: Run the installer and follow the simple on-screen instructions to set up the suite on your computer.
  3. 3. Open a project template: Launch WPS Spreadsheet, go to the template library, and search for 'Project Management' to instantly start tracking your tasks.
Completely free and lightweight office suiteFully compatible with Microsoft Excel, Word, and PowerPoint formatsRich selection of free project management and Gantt chart spreadsheet templatesFamiliar, easy-to-use tabbed interface with zero learning curve
microsoft office alternative - wps office

Frequently Asked Questions

What does 'ed' mean in Microsoft Project?

'ed' stands for elapsed days. When you use this format (e.g., 5ed), Microsoft Project calculates the duration based on a continuous 24-hour day, 7 days a week, ignoring any non-working time, weekends, or holidays defined in the project calendar.

Why do decimal days appear when I assign a specific resource?

Assigning a resource whose base calendar differs from the overall project calendar can cause partial days. If the resource works fewer hours per day than the project default, Microsoft Project calculates the task duration as a fraction of a standard day. Ensure resource calendars align with the project's default working times.

Can I change the default working hours in Microsoft Project?

Yes. You can change them by navigating to File > Options > Schedule. From there, adjust the 'Default start time', 'Default end time', and 'Hours per day' to match your specific custom calendar, which helps prevent unwanted decimal durations.