How to Schedule Tasks on Weekends in Project for the Web
Question details
The organization needs to schedule project activities on weekends, but cannot find a way to include Saturdays and Sundays in the workweek.

- Product
- Microsoft Project for the web
- Device & OS
- not provided
- Scenario
- Planning a project timeline for an organization that does not follow a standard Monday-to-Friday workweek.
- Observed behavior
- Project for the web does not provide a built-in, out-of-the-box option to schedule tasks or activities on weekends.
Keep in mind that Microsoft Project for the web defaults to a standard 5-day workweek. To utilize a 7-day schedule, you will need to rely on Microsoft's alternative project environments like Project Online.
Use Project Online to Configure a 7-Day Working Week
Since Project for the web lacks weekend scheduling, switching to Project Online allows you to fully customize working days.
Project Online provides comprehensive calendar customization features that are not currently available in the simplified Project for the web interface. If your organization has access to it, you can alter the base calendar to include weekends.
Log into your Microsoft 365 environment and launch Project Online instead of Project for the web.
Navigate to the project settings and look for the 'Change Working Time' option.
Select the Work Weeks tab, click on Details, and highlight Saturday and Sunday. Set these days to specific working times to establish a 7-day workweek for your activities.

Submit a Feature Request to Microsoft
Report your need for weekend scheduling directly to the development team to prioritize future updates.
Track 7-Day Project Schedules with WPS Office Templates
If Project for the web's rigid 5-day workweek is slowing you down, consider managing your tasks using highly customizable Gantt charts in WPS Spreadsheet. WPS Office offers a free, lightweight suite that gives you complete control over your timelines.
- 1. Install WPS Office: Download and install the free WPS Office suite on your device.
- 2. Open the Template Library: Launch WPS Spreadsheet and navigate to the homepage to access the built-in Template library.
- 3. Search for Project Trackers: Search for 'Gantt Chart' or 'Project Schedule' and download a template that fits your workflow.
- 4. Customize Dates: Edit the spreadsheet columns to include Saturdays and Sundays, ensuring your team can track weekend activities seamlessly.

Frequently Asked Questions
Can I change the default working hours in Project for the web?
Currently, Project for the web relies on a fixed Monday-to-Friday background calendar. To define custom working hours or days, you need to use Project Online or the Project desktop application.
Will my project end dates adjust if I work on weekends in Project for the web?
No. Because Project for the web does not recognize weekends as working days, tasks spanning over a weekend will automatically have their duration pushed to the following Monday, increasing the calendar days taken.
Is Project Online being replaced by Project for the web?
While Microsoft is continuously adding features to Project for the web, Project Online remains available for complex project management needs, such as custom calendars and enterprise resource planning.