Microsoft Project for the Web: Schedule Task Effort Over a Longer Duration

Olivia MillerOlivia Miller Nov 13, 2026 869 views

Question details

The user wants to schedule a small amount of assigned work across a longer task duration in Microsoft Project for the Web.

How to Schedule Task Effort Over a Longer Duration in Microsoft Project for the Web
Product
Microsoft Project for the Web
Device & OS
not provided
Scenario
An assigned task needs to span five days while requiring only three hours of effort.
Observed behavior
Changing duration or effort automatically changes the other value for the assigned task.
Before you start

Open the project and identify the task, its assigned resource, and the duration and effort you want to record. Check whether your current version allows the values to be edited independently, as product capabilities may change.

Solution 1Recommended

Track the Detailed Schedule in a Separate Spreadsheet

Use a spreadsheet to record a longer time window and a smaller amount of work when Project for the Web links the two values.

In the behavior described, assigned task effort and duration cannot be set independently to five days and three hours. A separate schedule records the intended values but does not change or automatically update the task in Project for the Web.

1
Review the task

Open the project in Project for the Web and select the assigned task to review its duration, effort, and resource.

2
Create a tracking table

Open a spreadsheet and add columns for task name, resource, start date, end date, and planned effort.

3
Record the intended schedule

Enter the five-day date range and three hours of planned effort in the task's row. Add a note identifying the corresponding Project task.

4
Maintain both records

Update the spreadsheet and the task in Project for the Web when the plan changes; the two records do not sync automatically.

Track the Detailed Schedule in a Separate Spreadsheet
Resource assignment: Changing or removing an assignment may alter task values or resource information. Review the result before relying on it as a workaround.
Free Microsoft Office alternative

Track Project Effort in WPS Spreadsheets

WPS Office is a free, lightweight Office alternative with a familiar interface. Use WPS Spreadsheets to maintain a separate effort-tracking table and move compatible Office files between applications. It does not change how Microsoft Project links effort and duration.

Track planned effort and task dates in a separate spreadsheetOpen and edit Microsoft Excel XLSX filesUse a familiar spreadsheet interface for an easier transitionWork with a free, lightweight Office suite
microsoft office alternative - wps office

Frequently Asked Questions

Can I assign three hours of work across five days in Project for the Web?

In the behavior described, assigned effort and duration are linked, so those values cannot be set independently. Check the task in your current version, then use a separate tracking table if the limitation remains.

Will removing the resource assignment let me keep the intended schedule?

Removing an assignment can change task values and removes the resource association. Review the task after any assignment change; do not assume it preserves the intended schedule.

Does a spreadsheet automatically update the Project task?

No. A separate spreadsheet is a manual tracking workaround unless you have set up a supported integration. Update both records when the plan changes.

Where can I request independent effort and duration settings?

Look for a feedback option under Help or settings in Project for the Web, or visit Microsoft Support to find the current feedback channel.