Schedule a Microsoft Project Task on a Project Nonworking Day

Steve KSteve K Nov 14, 2026 868 views

Question details

Schedule a task on Friday when the project calendar marks Friday as nonworking but the assigned resource is available.

Schedule a Microsoft Project Task on a Project Nonworking Day
Product
Microsoft Project
Device & OS
not provided
Scenario
A resource works on Fridays, but the project calendar excludes Fridays and the user does not want to change the schedule for every task.
Observed behavior
Microsoft Project may move the task from Friday to the next working day despite the resource's Friday availability.
Before you start

Check that the assigned resource's calendar includes working hours on Friday and that the task is automatically scheduled. If calendar editing is disabled, check whether your organization manages calendars centrally.

Solution 1Recommended

Apply a Friday Working-Day Calendar to the Task

Use a task calendar to allow Friday work for the affected task without changing the project calendar for every task.

A task calendar provides working time for the selected task. Project normally also considers the assigned resource's calendar, so both calendars should allow work on Friday.

1
Create a task calendar

Go to Project > Change Working Time and select Create New Calendar. Create a base calendar for tasks that can be scheduled on Friday.

2
Set Friday working hours

In Change Working Time, select the new calendar, open the Work Weeks tab, and choose Details. Select Friday, set it to the desired working hours, and click OK.

3
Assign the calendar to the task

Double-click the task to open Task Information. On the Advanced tab, select the new calendar in the Calendar list and click OK.

4
Check the schedule

Review the task's scheduled dates and resource assignment in the Gantt Chart. If the task still moves, check its constraints, dependencies, resource availability, and leveling settings.

Apply a Friday Working-Day Calendar to the Task
Keep resource availability in effect: Leave the option for scheduling to ignore resource calendars unchecked if Project should continue to respect the assigned resource's working hours. If resource leveling splits the remaining work, review the option to allow leveling to create splits in remaining work under Resource > Leveling Options; changing it can affect other tasks.
Free Microsoft Office alternative

Track Task Dates and Resource Availability in WPS Spreadsheet

WPS Office is a free, lightweight Office alternative with a familiar interface and Microsoft Office format compatibility for an easy transition. Use WPS Spreadsheet to maintain a manual task and resource-availability tracker; it does not change Microsoft Project calendars or replace Project's automatic scheduling.

Track task dates and resource availability in a spreadsheetOpen and edit Microsoft Excel XLSX filesWork in a familiar, easy-to-use Office interfaceUse a free, lightweight Office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why doesn't the resource's Friday calendar schedule the task on Friday by itself?

Project also considers the calendar used to schedule the task. If Friday is nonworking in the project calendar, assign a task calendar with Friday working hours through Task Information > Advanced.

Will a task calendar make Friday a working day for the whole project?

No. Assigning a custom calendar in Task Information > Advanced affects the selected task, not every task that uses the project calendar.

What if the calendar editing option is disabled?

Your organization may manage enterprise calendars centrally. Ask your Project administrator to create or update an appropriate calendar, or confirm whether you can create a local base calendar under Project > Change Working Time.

Do I need to assign the calendar to every affected task?

A task calendar applies only to tasks assigned that calendar. For each task that needs Friday scheduling, check its Calendar setting under Task Information > Advanced.

Should I tell Project to ignore resource calendars?

Usually not if the assigned resource already works on Friday. In Task Information > Advanced, leave the option to ignore resource calendars unchecked so Project continues to consider that resource's availability.