Set Task Start and Finish Dates in Microsoft Project
Question details
The user wants to schedule equipment tests using start and finish dates or a start date and duration.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- Equipment runs 24-hour tests with changing start times and durations, and the schedule should also record historical usage.
- Observed behavior
- The desired schedule calculates planned finish times and records actual test dates while accounting for continuous operation.
Decide whether you are planning a future test or recording a completed one. For continuous testing, check that the project and any assigned resources use calendars that permit work at the required times.
Schedule tests automatically using a start date and duration
Use this approach to calculate a planned finish time for a test while preserving automatic scheduling.
Entering planned dates on automatically scheduled tasks can create constraints. A start or finish constraint can affect how Project responds to predecessor and successor links, so review it when a task does not move as expected.
Entering both planned dates does not reliably make Project calculate the duration between them. For planning, enter a start and duration; for completed tests, record actual dates in the Tracking table.
In the Gantt Chart view, select the test tasks and choose Task > Auto Schedule.
Choose Project > Project Information and select the 24 Hours calendar if tests can run around the clock. Check assigned resource calendars as well, because they can affect scheduling.
In the Start column, enter the planned date and time. In the Duration column, enter the test length in hours, such as 36h, and check the calculated Finish value.
Double-click the task and open Task Information > Advanced to inspect its Constraint type and Constraint date. If a constraint prevents linked tasks from moving as intended, change it to an appropriate flexible constraint.

Record actual start and finish dates for completed tests
Use the Tracking table to record when a test actually ran rather than treating historical dates as planned constraints.
Track equipment test times in WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface and Microsoft Office format support for easy migration. Use WPS Spreadsheets to list test start and finish times and calculate elapsed time; it does not replace Microsoft Project's scheduling engine.

Frequently Asked Questions
Why doesn't a task move when its predecessor changes?
A constraint may be limiting the task's movement. Double-click the task and check Task Information > Advanced for its constraint type and date.
How can I schedule a test that runs overnight?
Choose Project > Project Information and select a calendar that allows work during the test, such as 24 Hours. Also check the calendars of any assigned resources.
Where do I enter the dates a test actually started and finished?
Choose View > Tables > Tracking, then enter the timestamps in Actual Start and Actual Finish. An actual finish marks the task as completed.
How do I display the time alongside each task date?
Choose File > Options > General and select a Date format that includes both the date and time.