The user wants to schedule equipment tests using start and finish dates or a start date and duration.

Set Task Start and Finish Dates in Microsoft Project
Product
Microsoft Project
Device & OS
not provided
Scenario
Equipment runs 24-hour tests with changing start times and durations, and the schedule should also record historical usage.
Observed behavior
The desired schedule calculates planned finish times and records actual test dates while accounting for continuous operation.
Before you start

Decide whether you are planning a future test or recording a completed one. For continuous testing, check that the project and any assigned resources use calendars that permit work at the required times.

Solution 1Recommended

Schedule tests automatically using a start date and duration

Use this approach to calculate a planned finish time for a test while preserving automatic scheduling.

Entering planned dates on automatically scheduled tasks can create constraints. A start or finish constraint can affect how Project responds to predecessor and successor links, so review it when a task does not move as expected.

Entering both planned dates does not reliably make Project calculate the duration between them. For planning, enter a start and duration; for completed tests, record actual dates in the Tracking table.

1
Enable automatic scheduling

In the Gantt Chart view, select the test tasks and choose Task > Auto Schedule.

2
Set a continuous calendar

Choose Project > Project Information and select the 24 Hours calendar if tests can run around the clock. Check assigned resource calendars as well, because they can affect scheduling.

3
Enter the start and duration

In the Start column, enter the planned date and time. In the Duration column, enter the test length in hours, such as 36h, and check the calculated Finish value.

4
Review scheduling constraints

Double-click the task and open Task Information > Advanced to inspect its Constraint type and Constraint date. If a constraint prevents linked tasks from moving as intended, change it to an appropriate flexible constraint.

Schedule tests automatically using a start date and duration
Show times: If the Start and Finish columns show only dates, choose File > Options > General and select a Date format that includes a time.
Free Microsoft Office alternative

Track equipment test times in WPS Spreadsheets

WPS Office is a free, lightweight Office alternative with a familiar interface and Microsoft Office format support for easy migration. Use WPS Spreadsheets to list test start and finish times and calculate elapsed time; it does not replace Microsoft Project's scheduling engine.

Calculate elapsed test time from start and finish timestampsOpen and edit Microsoft Excel XLSX filesUse a familiar spreadsheet interface for equipment logsWork with a free, lightweight Office alternative
microsoft office alternative - wps office

Frequently Asked Questions

Why doesn't a task move when its predecessor changes?

A constraint may be limiting the task's movement. Double-click the task and check Task Information > Advanced for its constraint type and date.

How can I schedule a test that runs overnight?

Choose Project > Project Information and select a calendar that allows work during the test, such as 24 Hours. Also check the calendars of any assigned resources.

Where do I enter the dates a test actually started and finished?

Choose View > Tables > Tracking, then enter the timestamps in Actual Start and Actual Finish. An actual finish marks the task as completed.

How do I display the time alongside each task date?

Choose File > Options > General and select a Date format that includes both the date and time.