Show a Combined Resource Graph for Microsoft Project Files
Question details
The user wants to view resources from multiple Microsoft Project files in a combined resource graph.

- Product
- Microsoft Project 2010
- Device & OS
- not provided
- Scenario
- Several projects need to be reviewed together in a master project using a split view.
- Observed behavior
- A Gantt Chart and Resource Graph split view may not reliably show resources from all subprojects, and certain split views with dynamic masters may cause crashes.
Place the project files and resource pool in one local folder and keep their names and locations stable. Identify the shared resource pool and check which resources should appear across the subprojects.
Create a static master and use a resource-based split view
Use this approach to inspect resources from multiple projects while avoiding the dynamic-master split views associated with instability.
A static master is a snapshot of the inserted projects. Later changes to the original subprojects do not automatically update the snapshot.
The Resource Graph normally displays the selected resource rather than all resources as a single combined chart. Select different resources in the upper pane to inspect them.
Open the resource pool and each subproject. In each subproject, choose Resource > Resource Pool > Share Resources, select Use resources, and choose the pool file.
Create a new project, then choose Project > Subproject. Select a subproject and clear Link to project in the Insert Project dialog before inserting it. Repeat for the remaining files.
In the master project, choose View > Resource Sheet or View > Resource Usage. Check that the expected resources and assignments are present, and review any duplicate resource entries.
On the View tab, enable Details in the Split View group and select Resource Graph for the lower pane. Select a resource in the upper pane to inspect its graph.

Check the resource view and filter before troubleshooting
Use this check if a resource group filter hides projects or the graph does not show the expected resource.
Use WPS Office for Project Reports and Supporting Documents
WPS Office is a free, lightweight alternative for everyday office work, with a familiar interface and compatibility with common Microsoft Office formats for easier migration. It does not fix Microsoft Project master files or replace the Project Resource Graph.

Frequently Asked Questions
Why use a static master instead of a dynamic master?
A static master avoids the live links used by a dynamic master, which may be unstable with certain split views. Clear Link to project in the Project > Subproject insertion dialog to create a static snapshot.
Does the Resource Graph show every resource at once?
The Resource Graph normally shows the selected resource. Use Resource Sheet or Resource Usage in the upper pane and select each resource to inspect its graph.
Why did my resource group filter hide projects in the Gantt Chart?
The filter may have been applied to the active task view. Select No Filter on the View tab, switch the upper pane to Resource Sheet or Resource Usage, and apply the resource filter there.
Will changes to my subprojects update a static master?
No. A static master is a snapshot. Create a fresh static master by inserting the updated subprojects again with Link to project cleared.
Can WPS Office repair a Microsoft Project resource graph?
No. Use Microsoft Project to configure the resource pool, master project, and split view. WPS Office can help with supporting spreadsheets and reports but does not repair Project files or provide the Project Resource Graph.