Track Late Deliverables in Microsoft Project for the Web Without Changing Planned Dates

Huma Ashraf ChHuma Ashraf Ch Nov 13, 2026 869 views

Question details

The user needs to record actual completion dates for late deliverables while retaining the originally projected finish dates.

Track Late Deliverables in Microsoft Project for the Web Without Changing Planned Dates
Product
Microsoft Project for the web
Device & OS
not provided
Scenario
Compare scheduled deliverable dates with actual completion dates without overwriting the dates used for the original plan.
Observed behavior
The desired outcome is to retain separate planned and actual finish dates. The record does not establish that the available Project for the web interface supports this tracking.
Before you start

Open the project and confirm which Microsoft interface you are using; a SharePoint Tasks list is not Project for the web. Decide whether the date you want to preserve is the original planned finish or the current forecast finish, because those serve different purposes.

Solution 1Recommended

Check for separate completion-date fields in your web project

Use this check to determine whether your current interface supports recording completion dates independently of scheduling dates.

Project for the web may not offer the same actual-date and baseline tracking as desktop Microsoft Project. Available controls can vary by interface and subscription, including projects accessed through Microsoft Planner.

1
Inspect the available task fields

Open your project in Grid view, select a deliverable, and inspect its task details and the available column controls. Look for a separate actual completion field rather than assuming that Finish records actual completion.

2
Verify scheduling behavior

If a separate actual completion field is available, test it on a noncritical task and check whether entering a date changes Finish or dependent task dates. Do not rely on it for independent tracking until you confirm its behavior.

3
Use a custom date field if supported

If the project offers an Add column or New field control with a Date type, create a field named Actual completion date. Enter the deliverable's completion date there rather than overwriting the scheduling Finish field.

Check for separate completion-date fields in your web project
A custom field is a manual record: A custom date field does not automatically provide native actual-finish tracking, baseline comparisons, or schedule variance calculations. It also does not freeze the current Finish date; preserve the original planned date separately if needed.
Free Microsoft Office alternative

Keep a Separate Deliverable Date Log in WPS Spreadsheet

WPS Office is a free, lightweight, easy-to-use Office alternative for maintaining a manual deliverable log. Its familiar spreadsheet interface and Excel format compatibility make it straightforward to move an existing date tracker into WPS. It does not fix Microsoft Project scheduling or replace Project's baseline engine, but it can keep planned and actual completion dates in separate columns.

Record deliverables, planned finish dates, and actual completion dates in separate spreadsheet columns.Open and save Microsoft Excel .xlsx and .xls tracker files.Use familiar spreadsheet controls for straightforward migration from an Excel-based log.Filter late deliverables and calculate date differences without editing the Microsoft Project schedule.
QA img-9

Frequently Asked Questions

Can I enter an actual finish date without changing the Finish date in Project for the web?

Do not assume that Finish is an independent actual-completion field. Open the task details and inspect the available columns for a separate completion field. If none exists, use a supported custom date field or a separate tracker for manual recording.

How do I keep the original deadline when a deliverable finishes late?

Keep the original deadline in a separate planned-date field or baseline. In desktop Microsoft Project, use Project > Set Baseline before recording progress, then compare Baseline Finish with Actual Finish. A baseline created after delays will preserve the current schedule, not automatically restore the original one.

Does a custom Actual completion date field provide full actual-finish tracking?

No. If your web interface supports custom Date fields, one can store the completion date manually, but it does not automatically supply baseline history or native schedule variance calculations. Check the available reporting features before relying on it for project controls.

Can WPS Spreadsheet track how many days a deliverable is late?

Yes, as a manual tracker. In WPS Spreadsheet, put Planned Finish in column B and Actual Finish in column C, then enter =IF(OR(B2="",C2=""),"",MAX(0,C2-B2)) in D2. Format column D as a number. This calculates calendar days late for completed deliverables, not working-day schedule variance.