Why Microsoft Project Summary Task Duration Shows Working Days
Question details
Understand why a Microsoft Project summary task shows a working-day duration and how to display the elapsed calendar-day count.

- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A user wants a summary task to show the number of calendar days from its start date through its finish date.
- Observed behavior
- The summary task's Duration field reflects scheduled working time rather than an inclusive count of calendar dates.
Check the summary task's Start and Finish dates and review the applicable working calendar under Project > Change Working Time. Decide whether you want to count both the start and finish dates.
Display calendar days in a Microsoft Project custom field
Use a custom number field to show the inclusive count of calendar dates without changing the scheduled Duration field.
Project calculates scheduled duration using working time, not a simple count of calendar dates. Under the Standard calendar, a working day normally contains eight working hours; weekends and other nonworking time can make the calendar span longer.
The formula below counts both the start and finish dates. It counts date boundaries rather than elapsed 24-hour periods.
In Microsoft Project, open your project and select Project > Custom Fields.
Under Task, select Number as the field type, choose an available field such as Number1, and use Rename to give it a label such as Calendar Days.
Select Formula and enter DateDiff("d",[Start],[Finish])+1, then confirm the formula.
In the custom field settings, select Use formula under Calculation for task and group summary rows, then select OK.
In a task table such as Gantt Chart, right-click a column heading, select Insert Column, and choose the custom number field.

Track project dates in WPS Spreadsheets
WPS Office is a free, lightweight Office alternative with a familiar interface and compatibility with common Microsoft Office formats, making it easy to move existing documents and spreadsheets. Use WPS Spreadsheets to track project dates and calculate calendar-day spans; it does not replace Microsoft Project's scheduling calculations.

Frequently Asked Questions
Why is the summary task duration shorter than the calendar span?
The built-in Duration field reflects scheduled working time. Weekends, holidays, and other nonworking periods may fall between the summary task's start and finish dates without adding working duration.
Does the calendar-day formula include both the start and finish dates?
Yes. DateDiff("d",[Start],[Finish])+1 counts both dates. Remove +1 if you want the difference between the dates without including the start date.
Why is my custom field blank on summary tasks?
Open Project > Custom Fields, select the custom field, and choose Use formula under Calculation for task and group summary rows.
Will the custom formula change my project schedule?
No. A custom number field displays a separate count; the built-in Duration, Start, and Finish fields remain governed by Project's scheduling settings and calendars.