Why Microsoft Project Summary Task Duration Shows Working Days

Elise WilliamsElise Williams Nov 22, 2026 869 views

Question details

Understand why a Microsoft Project summary task shows a working-day duration and how to display the elapsed calendar-day count.

Why Microsoft Project Summary Task Duration Shows Working Days
Product
Microsoft Project
Device & OS
not provided
Scenario
A user wants a summary task to show the number of calendar days from its start date through its finish date.
Observed behavior
The summary task's Duration field reflects scheduled working time rather than an inclusive count of calendar dates.
Before you start

Check the summary task's Start and Finish dates and review the applicable working calendar under Project > Change Working Time. Decide whether you want to count both the start and finish dates.

Solution 1Recommended

Display calendar days in a Microsoft Project custom field

Use a custom number field to show the inclusive count of calendar dates without changing the scheduled Duration field.

Project calculates scheduled duration using working time, not a simple count of calendar dates. Under the Standard calendar, a working day normally contains eight working hours; weekends and other nonworking time can make the calendar span longer.

The formula below counts both the start and finish dates. It counts date boundaries rather than elapsed 24-hour periods.

1
Open custom fields

In Microsoft Project, open your project and select Project > Custom Fields.

2
Choose a number field

Under Task, select Number as the field type, choose an available field such as Number1, and use Rename to give it a label such as Calendar Days.

3
Enter the formula

Select Formula and enter DateDiff("d",[Start],[Finish])+1, then confirm the formula.

4
Calculate summary rows

In the custom field settings, select Use formula under Calculation for task and group summary rows, then select OK.

5
Add the field to the view

In a task table such as Gantt Chart, right-click a column heading, select Insert Column, and choose the custom number field.

Display calendar days in a Microsoft Project custom field
Scheduled duration remains unchanged: The custom field displays a separate calendar-day count. It does not change the task calendar, scheduled dates, or built-in Duration field.
Free Microsoft Office alternative

Track project dates in WPS Spreadsheets

WPS Office is a free, lightweight Office alternative with a familiar interface and compatibility with common Microsoft Office formats, making it easy to move existing documents and spreadsheets. Use WPS Spreadsheets to track project dates and calculate calendar-day spans; it does not replace Microsoft Project's scheduling calculations.

Track project start and finish dates in a spreadsheetCalculate inclusive calendar-day spans with a spreadsheet formulaWork with Microsoft Excel XLSX files and other common Office formatsUse a familiar interface in a lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Why is the summary task duration shorter than the calendar span?

The built-in Duration field reflects scheduled working time. Weekends, holidays, and other nonworking periods may fall between the summary task's start and finish dates without adding working duration.

Does the calendar-day formula include both the start and finish dates?

Yes. DateDiff("d",[Start],[Finish])+1 counts both dates. Remove +1 if you want the difference between the dates without including the start date.

Why is my custom field blank on summary tasks?

Open Project > Custom Fields, select the custom field, and choose Use formula under Calculation for task and group summary rows.

Will the custom formula change my project schedule?

No. A custom number field displays a separate count; the built-in Duration, Start, and Finish fields remain governed by Project's scheduling settings and calendars.