Why Microsoft Project Time-Phases BCWP Through the Status Date
Question details
Understand why time-phased BCWP extends to the status date when earned value is based on Physical % Complete.
- Product
- Microsoft Project
- Device & OS
- not provided
- Scenario
- A task uses Physical % Complete to calculate earned value, and the user wants its BCWP history to reflect the task's actual finish.
- Observed behavior
- Microsoft Project may distribute incremental BCWP from the task start or previous status date through the current status date, even when that date is later than the scheduled finish.
Confirm that the task has a saved baseline and uses Physical % Complete as its earned value method. Check the task's Actual Finish and the project's current status date before updating the physical percentage.
Set the status date to the actual finish before updating Physical % Complete
Use this sequence when a task is ready for full earned value credit and you want to avoid spreading the final increment beyond its actual finish.
With Physical % Complete, Project recalculates time-phased BCWP when the physical percentage changes. It may spread the incremental earned value from the task start or previous status date through the current status date; this can be expected behavior rather than a calculation error.
In Gantt Chart view, add the Actual Finish column using Add New Column and verify the task's actual finish date.
Open Project > Status Date and enter the task's actual finish date. The status date applies to the whole project, so consider its effect on other reporting.
In Gantt Chart view, add the Physical % Complete column if needed, then set the task's value to 100% once it qualifies for full credit.
Open a time-phased view such as Task Usage and display BCWP to inspect the distribution. Return to Project > Status Date to set the date needed for subsequent reporting.
Review earned value reports in WPS Office
WPS Office is a free, lightweight alternative for working with exported project reports and other Office files. Its familiar interface and Microsoft Office format compatibility make it easy to move existing documents and spreadsheets. WPS does not change Microsoft Project's BCWP calculations.

Frequently Asked Questions
Why does BCWP extend past the scheduled finish?
When Physical % Complete changes, Project may distribute the incremental BCWP through the current status date, even if that date is later than the scheduled finish.
Where can I change the status date in Microsoft Project?
Select Project > Status Date and enter the date you need. The status date is project-wide and can affect reporting for other tasks.
When should I set Physical % Complete to 100%?
Set it to 100% when the task qualifies for full earned value credit. If the final BCWP increment should reflect the actual finish, set the status date to that finish before changing Physical % Complete.
Does Physical % Complete have to match schedule progress?
No. Physical % Complete can represent measurable output or acceptance independently of schedule progress. You can add the Physical % Complete column in Gantt Chart view to review or update it.




