Calculate Weekdays Between Two Dates in Acrobat JavaScript

Natalie TaylorNatalie Taylor Nov 24, 2026 868 views

Question details

Calculate the number of weekdays between two dates in a PDF form, excluding Saturdays and Sundays.

Calculate Weekdays Between Two Dates in Acrobat JavaScript
Product
Adobe Acrobat PDF forms
Device & OS
not provided
Scenario
A PDF form uses JavaScript to calculate a date difference, and the result should count only weekdays.
Observed behavior
The current calculation includes weekend days.
Before you start

Open the PDF in a version of Adobe Acrobat that can edit form fields. Check the names and date formats of the start and end fields; the example below uses StartDate, EndDate, and mm/dd/yyyy.

Solution 1Recommended

Count weekdays with a custom Acrobat form calculation

Use this script when the start and end dates should both be included if they fall on weekdays.

The script checks each date with getDay(), counting values 1 through 5 and skipping Saturday and Sunday. It handles partial weeks but does not exclude public holidays.

1
Check the date fields

In Acrobat, open Tools or All tools > Prepare a form. Open each date field's Properties and confirm its name and date format. Set or adapt the field names to StartDate and EndDate and use mm/dd/yyyy for this example.

2
Open the result calculation

Select or add the text field that will display the weekday count. Open Properties > Calculate, choose Custom calculation script, and select Edit.

3
Enter the script

Replace the calculation script with the following code, changing the field names or date format if needed: var startText = this.getField("StartDate").valueAsString; var endText = this.getField("EndDate").valueAsString; var format = "mm/dd/yyyy"; var result = ""; try { var start = util.scand(format, startText); var end = util.scand(format, endText); if (start && end && util.printd(format, start) === startText && util.printd(format, end) === endText && start <= end) { start.setHours(12, 0, 0, 0); end.setHours(12, 0, 0, 0); var count = 0; for (var day = new Date(start.getTime()); day <= end; day.setDate(day.getDate() + 1)) { var weekday = day.getDay(); if (weekday >= 1 && weekday <= 5) count++; } result = count; } } catch (e) { result = ""; } event.value = result;

4
Save and test the form

Close the script editor and field properties, save the PDF, and enter test dates in the two date fields. For example, 05/01/2026 through 05/04/2026 should return 2.

Count weekdays with a custom Acrobat form calculation
Date and range rules: The result is blank if a date is missing, does not match the specified format, or the start date is after the end date. Both endpoints are included when they are weekdays.
Free Microsoft Office alternative

Work with PDF and Office files in WPS Office

WPS Office is a free, lightweight alternative with a familiar interface and support for common Office formats, making it easy to move existing documents into your workflow. Acrobat form JavaScript must still be edited and tested in Acrobat.

Open and work with PDF files alongside Office documentsCompatible with Microsoft Word, Excel, and PowerPoint formats, including DOCX, XLSX, and PPTXUse a familiar interface for a smoother transitionAccess a free, lightweight office suite
microsoft office alternative - wps office

Frequently Asked Questions

Does the script include the start and end dates?

Yes. It counts each endpoint if it falls on a Monday through Friday. A same-day weekday range returns 1; a same-day weekend range returns 0.

Does this calculation exclude holidays?

No. The getDay() check excludes only Saturdays and Sundays. Excluding holidays requires an additional list of holiday dates and a check against that list.

Why is the result field blank?

Check that both date fields contain valid dates in mm/dd/yyyy format and that the start date is not later than the end date. In Prepare a form, also verify that the script's field names match the actual field names.

Where do I put the JavaScript in Acrobat?

Open Prepare a form, select the result text field, and go to Properties > Calculate > Custom calculation script > Edit. Paste the script there, rather than in either date field.